Skip to content
Gridcensus

Ward County, Texas · WECC

DC Readiness
49.0
Fair / 100

COYONOSA is a substation-adjacent datacenter candidate site in Ward County, Texas, interconnecting through WECC. It screens at 49.0/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCOYONOSA
Nearest grid bottleneckPALOUS_WOLFCA1_1 · 11 km (ERCOT)
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityTEXAS-NEW MEXICO POWER COinvestor ownedfavorable to large load · terms ≥ 75 MWSB 6 large-load provisions (≥75 MW)

Speed to power

Interconnection outlookConstrained
≈ 3.5 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth1,169
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Fiber providers1
Fiber coverage1.8%

Site characteristics

Land contactWard County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterIONIC Digital Cedarvale
DC distance33.5 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days2,600
Heating degree days1,800
Land price / acre$1,747

Regulatory climate

Favorablestate posture · as of 2026-08

No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track COYONOSA

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
63
Fiber connectivity12%
37
Energy cost10%
50
Water risk7%
44
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Ward County, ranked by DC Readiness.

Sites near COYONOSA
SiteTypeVoltageCapacityQueue waitScore
PERMIAN BASIN 345Substation-Adjacent345 kV600 MW3.5 yrs64.6
EC Near Permian BasinGreenfield——3.5 yrs59.1
EC Near Permian BasinGreenfield——3.5 yrs58.5
UNKNOWN301432Substation-Adjacent345 kV600 MW3.5 yrs58.4
EC Near Permian BasinGreenfield——3.5 yrs58.0
EC Near Permian BasinGreenfield——3.5 yrs57.9
EC Near Permian BasinGreenfield——3.5 yrs57.9
EC Near Permian BasinGreenfield——3.5 yrs57.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for COYONOSA, Ward County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.