Greenfield (ODESSA 345 - None)

Greenfield

Upton County, Texas · ERCOT

DC Readiness
47.5
Fair / 100

Greenfield (ODESSA 345 - None) is a greenfield datacenter candidate site in Upton County, Texas, interconnecting through ERCOT. It screens at 47.5/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationODESSA 345
Substation voltage345 kV
Available capacity600 MW

Speed to power

ISO / RTO regionERCOT
Queue depth8
Avg queue wait1.7 yrs

Connectivity

Fiber providers2
Fiber coverage23.7%

Site characteristics

Site typeGreenfield

Risk & environment

Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score45/100

Location context

Nearest datacenterIONIC Digital Cedarvale
DC distance80.1 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.47¢/kWh
Industrial electricity7.67¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$1,323

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
63
Fiber connectivity12%
21
Energy cost10%
50
Water risk8%
44
Natural hazard8%
45
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Upton County, ranked by DC Readiness.

Sites near Greenfield (ODESSA 345 - None)
SiteTypeVoltageCapacityQueue waitScore
WAYMARKSubstation-Adjacent345 kV600 MW1.7 yrs53.8
NORTH MCCAMEYSubstation-Adjacent345 kV600 MW1.7 yrs53.8
UNKNOWN304698Substation-Adjacent138 kV100 MW1.7 yrs48.0
INDIAN MESASubstation-Adjacent138 kV100 MW1.7 yrs48.0
WEST YATES TAPSubstation-Adjacent138 kV100 MW1.7 yrs48.0
WEST YATES SWITCHSubstation-Adjacent138 kV100 MW1.7 yrs48.0
UNKNOWN309438Substation-Adjacent138 kV100 MW1.7 yrs48.0
MESA VIEW SWITCHSubstation-Adjacent138 kV100 MW1.7 yrs48.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (ODESSA 345 - None), Upton County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.