Montgomery, Texas · MISO

DC Readiness
58.9
Good / 100

At a glance

CONROE BULK is a substation-adjacent datacenter candidate site in Montgomery, Texas, scoring 58.9/100 DC Readiness — 26th of 74 scored sites in the county. Its nearest substation is CONROE BULK (0 mi, 138 kV). It sits in the MISO grid region and the ENTERGY TEXAS INC. service territory, where interconnection has averaged 3.5 years from request to operation. GridCensus catalogs 100 MW of candidate capacity here.

Power & interconnection

Nearest substationCONROE BULK
Nearest grid bottleneckCOLLE_JUPIT_1 · 73 km (ERCOT)
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
UtilityENTERGY TEXAS INC.investor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.5 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPStream Data Centers - Houston I
IXP distance7.9 mi
Fiber providers18
Fiber coverage94.2%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterStream Data Centers Houston
DC distance7.9 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.01¢/kWh
Industrial electricity7.45¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$13,070

Regulatory climate

Favorablestate posture · as of 2026-08

No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track CONROE BULK

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does CONROE BULK compare with other sites in Montgomery?

CONROE BULK ranks 26th of 74 scored candidate sites in Montgomery. Its 58.9/100 is roughly in line with the county average of 57.6. It is roughly in line with the Texas average of 56.4 and about 11% above the national average of 53.2.

Against the Texas average, its strongest sub-score is fiber connectivity (93 vs 71) and its weakest is speed to power (59 vs 72). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is CONROE BULK to power, fiber and other datacenters?

The nearest mapped substation, CONROE BULK, is about 0 miles away and operates at 138 kV. The nearest located transmission bottleneck is COLLE_JUPIT_1 (ERCOT), 45 miles away. For connectivity, the nearest internet exchange facility is Stream Data Centers - Houston I at 7.9 miles. 18 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Stream Data Centers Houston, 7.9 miles away.

What are the flood, water and hazard risks at CONROE BULK?

At the county level, FEMA's National Risk Index rates Montgomery "Very High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
59
Fiber connectivity12%
93
Energy cost10%
50
Water risk7%
44
Natural hazard6%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Montgomery, ranked by DC Readiness.

Sites near CONROE BULK
SiteTypeVoltageCapacityQueue waitScore
ROTHWOODSubstation-Adjacent345 kV600 MW3.5 yrs66.1
OAK RIDGESubstation-Adjacent345 kV600 MW3.5 yrs66.1
KUYKENDAHLSubstation-Adjacent345 kV600 MW3.5 yrs65.1
TOMBALLSubstation-Adjacent345 kV600 MW3.5 yrs64.8
UNKNOWN302822Substation-Adjacent230 kV300 MW3.5 yrs62.6
ConroeBrownfield138 kV3 MW3.5 yrs61.1
EC Near ConroeGreenfield——3.5 yrs60.5
GOSLINGSubstation-Adjacent138 kV100 MW3.5 yrs60.5

CONROE BULK: common questions

What is the DC Readiness score of CONROE BULK?

CONROE BULK scores 58.9/100 on the GridCensus DC Readiness scale, rated good. It ranks 26th of 74 scored sites in Montgomery. The Montgomery average is 57.6 and the Texas average is 56.4.

What is the nearest substation to CONROE BULK?

The nearest mapped substation is CONROE BULK, about 0 miles away, at 138 kV. GridCensus catalogs 100 MW of candidate capacity for the site.

Which electric utility serves CONROE BULK?

ENTERGY TEXAS INC. (investor owned) holds the retail service territory that contains the site; its holding company is ENTERGY CORP.

What grid region is CONROE BULK in?

CONROE BULK is in the MISO region. Projects interconnecting there have averaged a 3.5-year wait from queue request to operation.

How far is CONROE BULK from an internet exchange?

The nearest internet exchange facility is Stream Data Centers - Houston I, about 7.9 miles away; 18 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “CONROE BULK, Montgomery, TX”, https://gridcensus.com/datacenter-sites/texas/montgomery/conroe-bulk-6784b9ab (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for CONROE BULK, Montgomery is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.