TOMBALL
Substation-AdjacentMontgomery, Texas · ERCOT
TOMBALL is a substation-adjacent datacenter candidate site in Montgomery, Texas, interconnecting through ERCOT. It screens at 60.7/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.
Power & interconnection
Speed to power
Shorter queues and healthier completion here — a faster path to energization than the national norm.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
No moratorium; fastest US interconnection (ERCOT). SB 6 adds large-load obligations above 75 MW.
SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
Site location
Get alerts
Track TOMBALL
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Montgomery, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| OAK RIDGE | Substation-Adjacent | 345 kV | 600 MW | 1.7 yrs | 62.0 |
| ROTHWOOD | Substation-Adjacent | 345 kV | 600 MW | 1.7 yrs | 62.0 |
| KUYKENDAHL | Substation-Adjacent | 345 kV | 600 MW | 1.7 yrs | 61.0 |
| Conroe | Brownfield | 138 kV | 3 MW | 3.4 yrs | 60.0 |
| Security | Brownfield | 138 kV | 3 MW | 3.4 yrs | 59.2 |
| EC Near Conroe | Greenfield | — | — | 3.4 yrs | 58.8 |
| EC Near Conroe | Greenfield | — | — | 3.4 yrs | 58.8 |
| UNKNOWN302822 | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 58.5 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for TOMBALL, Montgomery. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.