EC Near Jack Fusco Energy Center
GreenfieldFort Bend County, Texas · ERCOT
At a glance
EC Near Jack Fusco Energy Center is a greenfield datacenter candidate site in Fort Bend County, Texas, scoring 59.7/100 DC Readiness — 45th of 61 scored sites in the county. It sits in the ERCOT grid region and the CENTERPOINT ENERGY service territory, where interconnection has averaged 3.5 years from request to operation.
Power & interconnection
Speed to power
Texas note: Since August 3, 2026, ERCOT has paused approvals to energize new datacenter and crypto-mining loads of 75 MW or more until a verification audit and a community impact review are complete; both reports are due to the Public Utility Commission of Texas by December 10, 2026. ERCOT speed-to-power scores here were set before the pause and do not reflect it. ERCOT board update.
Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.
SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
Site location
Get alerts
Track EC Near Jack Fusco Energy Center
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
How does EC Near Jack Fusco Energy Center compare with other sites in Fort Bend County?
EC Near Jack Fusco Energy Center ranks 45th of 61 scored candidate sites in Fort Bend County. Its 59.7/100 is roughly in line with the county average of 61.4. It is roughly in line with the Texas average of 56.4 and about 12% above the national average of 53.2.
Against the Texas average, its strongest sub-score is fiber connectivity (79 vs 71) and its weakest is power availability (30 vs 46). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.
How close is EC Near Jack Fusco Energy Center to power, fiber and other datacenters?
The nearest located transmission bottleneck is BI_SMR98_A (ERCOT), 3 miles away. For connectivity, the nearest internet exchange facility is Databank Houston Galleria (HOU5) at 23.4 miles. 15 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Rice Data Center, 19.3 miles away.
What are the flood, water and hazard risks at EC Near Jack Fusco Energy Center?
The site is in FEMA flood zone AE, a Special Flood Hazard Area — land with at least a 1% annual chance of flooding. WRI rates baseline water stress at 2.80 on a 0–5 scale. No mapped wetlands are recorded on the parcel. At the county level, FEMA's National Risk Index rates Fort Bend County "Very High".
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Fort Bend County, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| O'BRIEN | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 68.2 |
| SMITHERS | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 67.7 |
| W.A. PARISH (138KV) | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 66.7 |
| EC Near Imperial Power Plant LLC | Greenfield | — | — | 3.5 yrs | 66.5 |
| EC Near Jack Fusco Energy Center | Greenfield | — | — | 3.5 yrs | 66.2 |
| FRANZ | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 66.1 |
| EC Near Imperial Power Plant LLC | Greenfield | — | — | 3.5 yrs | 65.5 |
| OZ Fort Bend | Greenfield | — | — | 3.5 yrs | 64.6 |
EC Near Jack Fusco Energy Center: common questions
What is the DC Readiness score of EC Near Jack Fusco Energy Center?
EC Near Jack Fusco Energy Center scores 59.7/100 on the GridCensus DC Readiness scale, rated good. It ranks 45th of 61 scored sites in Fort Bend County. The Fort Bend County average is 61.4 and the Texas average is 56.4.
Which electric utility serves EC Near Jack Fusco Energy Center?
CENTERPOINT ENERGY (investor owned) holds the retail service territory that contains the site; its holding company is CENTERPOINT ENERGY INC.
What grid region is EC Near Jack Fusco Energy Center in?
EC Near Jack Fusco Energy Center is in the ERCOT region. Projects interconnecting there have averaged a 3.5-year wait from queue request to operation.
Is EC Near Jack Fusco Energy Center in a flood zone?
The site is in FEMA flood zone AE, a Special Flood Hazard Area — land with at least a 1% annual chance of flooding.
Who owns EC Near Jack Fusco Energy Center?
Parcel records list the owner as George Foundation (private land).
How far is EC Near Jack Fusco Energy Center from an internet exchange?
The nearest internet exchange facility is Databank Houston Galleria (HOU5), about 23.4 miles away; 15 fiber providers report service at the location.
Related pages
About this data
Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “EC Near Jack Fusco Energy Center, Fort Bend County, TX”, https://gridcensus.com/datacenter-sites/texas/fort-bend-county/ec-near-jack-fusco-energy-center-3f01760c (data as of October 10, 2026).
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
Every site and score for EC Near Jack Fusco Energy Center, Fort Bend County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.