EC Near Spencer
GreenfieldDenton County, Texas · ERCOT
EC Near Spencer is a greenfield datacenter candidate site in Denton County, Texas, interconnecting through ERCOT. It screens at 59.3/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.
Power & interconnection
Speed to power
Texas note: Since August 3, 2026, ERCOT has paused approvals to energize new datacenter and crypto-mining loads of 75 MW or more until a verification audit and a community impact review are complete; both reports are due to the Public Utility Commission of Texas by December 10, 2026. ERCOT speed-to-power scores here were set before the pause and do not reflect it. ERCOT board update.
Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.
SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
Site location
Get alerts
Track EC Near Spencer
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Denton County, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| CARROLLTON FRANKFORD | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 69.4 |
| LEWISVILLE SWITCH | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 69.0 |
| UNKNOWN310303 | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 68.8 |
| UNKNOWN304847 | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 68.3 |
| DFW Gas Recovery | Brownfield | 14 kV | 12 MW | 3.5 yrs | 68.2 |
| DENTON WEST INTERCHANGE | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 68.0 |
| EC Near Spencer | Greenfield | — | — | 3.5 yrs | 67.4 |
| COOPER CREEK | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 67.0 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
Every site and score for EC Near Spencer, Denton County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.