OZ Cherokee

Greenfield

Cherokee County, Texas · ERCOT

DC Readiness
60.1
Good / 100

OZ Cherokee is a greenfield datacenter candidate site in Cherokee County, Texas, interconnecting through ERCOT. It screens at 60.1/100 DC Readiness and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneERCOT_CENTRAL
Wholesale LMP$18.75/MWh
Utility commercial rate0.14¢/kWh
UtilityONCOR ELECTRIC DELIVERY COMPANY LLCinvestor ownedfavorable to large load · terms ≥ 75 MWERCOT connect-and-manage + SB 6 large-load provisions (≥75 MW)

Speed to power

Interconnection outlookConstrained
≈ 3.1 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionERCOT
Queue depth1,198
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPHouston Bunker
IXP distance87.6 mi
Fiber providers8
Fiber coverage80.4%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance136.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerOdom Charles A
Land contactCherokee County Assessor
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score45/100
Construction cost index76.5 (avg 100)

Location context

Nearest datacenterDatacenter 01457383500
DC distance25.4 mi
Nearest rail17.9 mi
Nearest gas pipeline6.8 mi
Nearest fiber route69.8 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity14.07¢/kWh
Industrial electricity6.36¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$4,007

Regulatory climate

Favorablestate posture · as of 2026-08

No moratorium; fastest US interconnection (ERCOT). SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track OZ Cherokee

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
78
Fiber connectivity12%
60
Energy cost10%
90
Water risk7%
44
Natural hazard6%
45
Buildability7%
75
Labor market4%
50
DC cluster4%
65
Land / acreage3%
51
Construction cost3%
86
Gas pipeline2%
78
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Cherokee County, ranked by DC Readiness.

Sites near OZ Cherokee
SiteTypeVoltageCapacityQueue waitScore
STRYKER CREEKSubstation-Adjacent345 kV600 MW1.7 yrs61.1
EC FFE Cherokee CountyGreenfield——3.4 yrs59.3
UNKNOWN305033Substation-Adjacent138 kV100 MW1.7 yrs57.5
UNKNOWN303218Substation-Adjacent138 kV100 MW1.7 yrs56.3
UNKNOWN302132Substation-Adjacent138 kV100 MW1.7 yrs56.2
UNKNOWN302286Substation-Adjacent138 kV100 MW1.7 yrs56.0
UNKNOWN300356Substation-Adjacent138 kV100 MW1.7 yrs55.9
UNKNOWN305952Substation-Adjacent138 kV100 MW1.7 yrs55.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.