Datacenter Sites in Weakley County, Tennessee
Weakley County has 24 scored datacenter candidate sites averaging 60.8/100 DC Readiness, with a catalogued aggregate of 7,100 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
24
Candidate sites
60.8/100
Avg DC Readiness
7,100 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Weakley County
Yessales_tax_exemption
Datacenter tax incentive
10.25¢/kWh
Commercial electricity
6.79¢/kWh
Industrial electricity
3
Fiber providers
Low
Water stress
$4,680
Land price / acre
1,600
Cooling degree days
3,600
Heating degree days
58°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.
By site type
Top datacenter sites in Weakley County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LAGOON CREEK | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 76.7 |
| GLEASON | Substation-Adjacent | 500 kV | 1,000 MW | 3.7 yrs | 76.0 |
| Greenfield (JOHNSONVILLE - GLEASON) | Greenfield | 500 kV | 1,000 MW | 3.7 yrs | 72.7 |
| WEAKLEY | Substation-Adjacent | 500 kV | 1,000 MW | 3.7 yrs | 72.2 |
| TAP152134 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 70.8 |
| Greenfield (WEAKLEY - GLEASON) | Greenfield | 500 kV | 1,000 MW | 3.7 yrs | 68.9 |
| MARTIN | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 68.2 |
| PIERCE | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 64.3 |
| Greenfield (MARTIN - TAP152134) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 63.1 |
| TAP170525 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 63.1 |
| Greenfield (WEAKLEY - LAGOON CREEK) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 63.1 |
| Greenfield (WEAKLEY - UNION CITY) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 61.8 |
| Greenfield (WEAKLEY - TAP154678) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 61.4 |
| Greenfield (WEAKLEY - UNION CITY) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 60.7 |
| OZ Weakley | Greenfield | — | — | 3.7 yrs | 60.3 |
| Greenfield (TAP152134 - TAP152211) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 59.4 |
| Greenfield (TAP154680 - TAP154681) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 56.6 |
| Greenfield (DYERSBURG - WEAKLEY) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 53.5 |
| Mine Site | Former Mine | — | — | — | 48.5 |
| Mine Site | Former Mine | — | — | — | 48.5 |
| Mine Site | Former Mine | — | — | — | 48.5 |
| Mine Site | Former Mine | — | — | — | 48.4 |
| Mine Site | Former Mine | — | — | — | 48.3 |
| Dresden Pad Ready Site | Shovel-Ready | — | — | — | 43.6 |
Weakley County datacenter FAQ
- How many datacenter sites are in Weakley County?
- 24 scored datacenter candidate sites, averaging 60.8/100 DC Readiness.
- Does Weakley County offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.
- What is the natural-hazard risk in Weakley County?
- FEMA's National Risk Index rates Weakley County as "Relatively High" (score 38).
- What are industrial electricity rates in Weakley County?
- Average industrial electricity is 6.79¢/kWh and commercial is 10.25¢/kWh in Weakley County.
Dataset updated . Screening estimates derived from public data sources.