DC Readiness
59.5
Good / 100

GREAT FALLS is a substation-adjacent datacenter candidate site in Warren County, Tennessee, interconnecting through SERC. It screens at 59.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationGREAT FALLS
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPPeace Communications CHA1
IXP distance56.5 mi
Fiber providers4
Fiber coverage94.5%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score62/100

Location context

Nearest datacenterTennessee South Data Center
DC distance49.8 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.64¢/kWh
Industrial electricity6.60¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$6,580

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power15%
75
Fiber connectivity12%
45
Energy cost10%
50
Water risk8%
90
Natural hazard8%
62
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
47
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Warren County, ranked by DC Readiness.

Sites near GREAT FALLS
SiteTypeVoltageCapacityQueue waitScore
EC FFE Warren CountyGreenfield3.7 yrs63.0
OZ WarrenGreenfield3.7 yrs62.0
EC Coal Warren CountyGreenfield3.7 yrs60.1
EAST MCMINNVILLESubstation-Adjacent161 kV100 MW1.0 yrs59.5
MCMINNVILLESubstation-Adjacent161 kV100 MW1.0 yrs59.5
MORRISONSubstation-Adjacent161 kV100 MW1.0 yrs59.5
TAP155439Substation-Adjacent161 kV100 MW1.0 yrs59.5
TAP152982Substation-Adjacent161 kV100 MW1.0 yrs59.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for GREAT FALLS, Warren County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.