Highmore Auditorium

Industrial

Hyde County, South Dakota · SPP

DC Readiness
53.0
Fair / 100

Highmore Auditorium is an industrial datacenter candidate site in Hyde County, South Dakota, interconnecting through SPP. It screens at 53.0/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityNORTHWESTERN ENERGY - (SD)investor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth4
Avg queue wait3.3 yrs

Connectivity

Nearest IXPELN02
IXP distance111.6 mi
Fiber providers2
Fiber coverage100.0%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score78/100

Location context

Nearest datacenterDatacenter 1422191469
DC distance111.5 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (no_income_tax)
Commercial electricity9.89¢/kWh
Industrial electricity7.77¢/kWh
Cooling degree days700
Heating degree days7,300
Land price / acre$2,117

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: No state corporate income tax; no personal income tax; no personal property tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Highmore Auditorium

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
58
Fiber connectivity12%
75
Energy cost10%
50
Water risk7%
76
Natural hazard6%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Hyde County, ranked by DC Readiness.

Sites near Highmore Auditorium
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN133185Substation-Adjacent230 kV300 MW3.3 yrs62.5
EC Near Future CTGreenfield——1.0 yrs61.6
EC Near HighmoreGreenfield——1.0 yrs61.5
EC Near Future CTGreenfield——1.0 yrs61.0
EC Near Future CTGreenfield——1.0 yrs61.0
EC Near HighmoreGreenfield——1.0 yrs60.9
EC Near Future CTGreenfield——1.0 yrs60.8
EC Near Future CTGreenfield——1.0 yrs60.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Highmore Auditorium, Hyde County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.