UNKNOWN159632

Substation-Adjacent

Faulk County, South Dakota · SPP

DC Readiness
57.7
Good / 100

UNKNOWN159632 is a substation-adjacent datacenter candidate site in Faulk County, South Dakota, interconnecting through SPP. It screens at 57.7/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN159632
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityNORTHWESTERN ENERGY - (SD)investor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth3
Avg queue wait3.3 yrs

Connectivity

Nearest IXPELN02
IXP distance61.0 mi
Fiber providers5
Fiber coverage97.7%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score78/100

Location context

Nearest datacenterDatacenter 1422191469
DC distance60.9 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (no_income_tax)
Commercial electricity11.10¢/kWh
Industrial electricity9.33¢/kWh
Cooling degree days700
Heating degree days7,300
Land price / acre$3,320

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: No state corporate income tax; no personal income tax; no personal property tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 4 nearby

Get alerts

Track UNKNOWN159632

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
59
Fiber connectivity12%
62
Energy cost10%
50
Water risk7%
76
Natural hazard6%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Faulk County, ranked by DC Readiness.

Sites near UNKNOWN159632
SiteTypeVoltageCapacityQueue waitScore
TAP159631Substation-Adjacent69 kV50 MW3.3 yrs56.9
UNKNOWN159638Substation-Adjacent69 kV50 MW3.3 yrs56.8
UNKNOWN159637Substation-Adjacent69 kV50 MW3.3 yrs54.9
UNKNOWN159633Substation-Adjacent69 kV50 MW3.3 yrs54.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for UNKNOWN159632, Faulk County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.