EC Coal Elk County

Greenfield

Elk County, Pennsylvania · PJM

DC Readiness
57.1
Good / 100

EC Coal Elk County is a greenfield datacenter candidate site in Elk County, Pennsylvania, interconnecting through PJM. It screens at 57.1/100 DC Readiness and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_PECO
Wholesale LMP$38.56/MWh

Speed to power

ISO / RTO regionPJM
Queue depth411
Avg queue wait3.0 yrs
Recent queue wait1.6 yrs
Completion rate19%
Withdrawal rate81%

Connectivity

Nearest IXPWindstream - State College
IXP distance53.8 mi
Fiber providers4
Fiber coverage68.6%
Nearest cloud providerGCP
Nearest cloud regionus-east5
Cloud region distance104.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerWEST PENN POWER CO
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index80.3 (avg 100)

Location context

Nearest datacenterVerizon
DC distance39.7 mi
Nearest rail2.5 mi
Nearest gas pipeline0.1 mi
Nearest fiber route49.4 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days800
Heating degree days5,600
Land price / acre$5,329

Incentive detail: Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
42
Fiber connectivity12%
67
Energy cost10%
75
Water risk8%
90
Natural hazard8%
72
Buildability7%
40
Labor market4%
50
DC cluster4%
45
Land / acreage3%
47
Construction cost3%
83
Gas pipeline2%
100
Tax incentive2%
100
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Elk County, ranked by DC Readiness.

Sites near EC Coal Elk County
SiteTypeVoltageCapacityQueue waitScore
FORESTSubstation-Adjacent230 kV300 MW3.0 yrs70.6
ELKOSubstation-Adjacent230 kV300 MW3.0 yrs67.8
Greenfield (HOMER CITY - FIVE MILE)Greenfield345 kV600 MW3.0 yrs66.8
UNKNOWN124301Substation-Adjacent138 kV100 MW3.0 yrs66.3
Greenfield (HOMER CITY - FIVE MILE)Greenfield345 kV600 MW3.0 yrs65.9
Greenfield (HOMER CITY - FIVE MILE)Greenfield345 kV600 MW3.0 yrs64.8
UNKNOWN124296Substation-Adjacent115 kV100 MW3.0 yrs63.9
CARBON CENTERSubstation-Adjacent138 kV100 MW3.0 yrs63.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Elk County, Elk County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.