Skip to content
Gridcensus

Muskogee County, Oklahoma · SPP

DC Readiness
66.9
Good / 100

MUSKOGEE is a substation-adjacent datacenter candidate site in Muskogee County, Oklahoma, interconnecting through SPP. It screens at 66.9/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationMUSKOGEE
Nearest grid bottleneckTMP270_23432 · 126 km (SPP)
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
UtilityOKLAHOMA GAS & ELECTRIC COinvestor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth118
Avg queue wait3.3 yrs

Connectivity

Nearest IXPLake Region Technology & Communications
IXP distance14.8 mi
Fiber providers10
Fiber coverage87.7%

Site characteristics

Former usegas
Existing capacity173 MW
Retirement date2010-12-01

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score58/100

Location context

Nearest datacenterLake Region Technology & Communications
DC distance14.8 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.69¢/kWh
Industrial electricity7.36¢/kWh
Cooling degree days1,900
Heating degree days3,600
Land price / acre$2,977

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track MUSKOGEE

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power20%
60
Fiber connectivity12%
88
Energy cost10%
50
Water risk7%
64
Natural hazard6%
58
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
30

Nearby comparable sites

Other scored datacenter candidate sites in Muskogee County, ranked by DC Readiness.

Sites near MUSKOGEE
SiteTypeVoltageCapacityQueue waitScore
TAP149385Substation-Adjacent345 kV600 MW3.3 yrs64.8
PECAN CREEKSubstation-Adjacent345 kV600 MW3.3 yrs64.8
EC Near MuskogeeGreenfield——3.5 yrs64.6
TAP148807Substation-Adjacent345 kV600 MW3.3 yrs64.4
EC Near MuskogeeGreenfield——3.5 yrs62.2
EC Near MuskogeeGreenfield——3.5 yrs62.0
EC Near MuskogeeGreenfield——3.5 yrs61.8
UNKNOWN119166Substation-Adjacent161 kV100 MW3.3 yrs60.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for MUSKOGEE, Muskogee County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.