EC Near Bowling Green

Greenfield

Wood County, Ohio · PJM

DC Readiness
62.0
Good / 100

EC Near Bowling Green is a greenfield datacenter candidate site in Wood County, Ohio, interconnecting through PJM. It screens at 62.0/100 DC Readiness and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPAmplex DC0
IXP distance12.9 mi
Fiber providers8
Fiber coverage44.6%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance108.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerBostdorff James F Trustee
Parcel APNJ34-610-270000016000
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usenear retired oil plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteADJUSTO CORP
Hazard sub-score60/100
Construction cost index96.5 (avg 100)

Location context

Nearest datacenterMeta Bowling Green Data Center
DC distance3.3 mi
Nearest rail1.5 mi
Nearest gas pipeline1.8 mi
Nearest fiber route120.5 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.49¢/kWh
Industrial electricity8.30¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$8,146

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
51
Fiber connectivity12%
77
Energy cost10%
84
Water risk8%
90
Natural hazard8%
60
Buildability7%
65
Labor market4%
50
DC cluster4%
85
Land / acreage3%
42
Construction cost3%
70
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Wood County, ranked by DC Readiness.

Sites near EC Near Bowling Green
SiteTypeVoltageCapacityQueue waitScore
LEMOYNESubstation-Adjacent345 kV600 MW2.2 yrs78.8
LEMOYNESubstation-Adjacent345 kV600 MW3.2 yrs77.0
UNKNOWN113650Substation-Adjacent345 kV600 MW3.2 yrs73.6
UNKNOWN156850Substation-Adjacent345 kV600 MW3.2 yrs70.9
Greenfield (FOSTORIA CENTRAL SUBSTATION - )Greenfield345 kV600 MW3.2 yrs70.8
Greenfield (LEMOYNE - UNKNOWN156850)Greenfield345 kV600 MW3.2 yrs70.3
WATERVILLESubstation-Adjacent138 kV100 MW3.2 yrs70.1
TAP137328Substation-Adjacent138 kV100 MW3.2 yrs69.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Bowling Green, Wood County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.