Skip to content
Gridcensus

Greenfield (UNKNOWN114784 - EAST LEIPSIC S)

Greenfield

Putnam County, Ohio · PJM

DC Readiness
51.5
Fair / 100

Greenfield (UNKNOWN114784 - EAST LEIPSIC S) is a greenfield datacenter candidate site in Putnam County, Ohio, interconnecting through PJM. It screens at 51.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN114784
Substation voltage138 kV
Available capacity100 MW

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait3.8 yrs

Connectivity

Nearest IXPMicrotronix Datacenter Ottoville
IXP distance18.3 mi
Fiber providers14
Fiber coverage54.1%

Site characteristics

Site typeGreenfield

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterMicrotronix Datacenter Ottoville
DC distance18.3 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.94¢/kWh
Industrial electricity8.76¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$8,403

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 5 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
45
Fiber connectivity12%
54
Energy cost10%
50
Water risk8%
90
Natural hazard8%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Putnam County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN114784 - EAST LEIPSIC S)
SiteTypeVoltageCapacityQueue waitScore
NORTH DELPHOSSubstation-Adjacent138 kV100 MW3.8 yrs62.6
UNKNOWN171445Substation-Adjacent138 kV100 MW3.8 yrs58.1
TAP171444Substation-Adjacent138 kV100 MW3.8 yrs57.9
UNKNOWN148486Substation-Adjacent138 kV100 MW3.8 yrs56.6
Greenfield (YELLOW CREEK SUBSTATION - TAP1)Greenfield138 kV100 MW3.8 yrs51.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN114784 - EAST LEIPSIC S), Putnam County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.