EC Near Ottawa County Project

Greenfield

Ottawa County, Ohio · PJM

DC Readiness
54.9
Fair / 100

EC Near Ottawa County Project is a greenfield datacenter candidate site in Ottawa County, Ohio, interconnecting through PJM. It screens at 54.9/100 DC Readiness and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPAmplex DC0
IXP distance23.5 mi
Fiber providers8
Fiber coverage44.6%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance114.5 mi

Site characteristics

Site typeGreenfield
Parcel ownerAMERICAN TRANSMISSION SYSTEMS, INC.
Land owner typeprivate
Buildability5.0/100
Land cover (NLCD)Water
Former usenear retired gas plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score60/100
Construction cost index96.5 (avg 100)

Location context

Nearest datacenterAligned Data Centers DC
DC distance20.8 mi
Nearest rail3.0 mi
Nearest gas pipeline8.5 mi
Nearest fiber route81.2 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.99¢/kWh
Industrial electricity7.20¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$7,882

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
51
Fiber connectivity12%
67
Energy cost10%
84
Water risk8%
84
Natural hazard8%
60
Buildability7%
5
Labor market4%
50
DC cluster4%
65
Land / acreage3%
42
Construction cost3%
70
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Ottawa County, ranked by DC Readiness.

Sites near EC Near Ottawa County Project
SiteTypeVoltageCapacityQueue waitScore
Greenfield (UNKNOWN113613 - DAVIS-BESSE)Greenfield345 kV600 MW3.2 yrs67.1
Greenfield (UNKNOWN113830 - DAVIS-BESSE)Greenfield345 kV600 MW3.2 yrs66.2
DAVIS-BESSESubstation-Adjacent345 kV600 MW3.2 yrs65.7
UNKNOWN114975Substation-Adjacent138 kV100 MW3.2 yrs65.3
Greenfield (UNKNOWN113830 - LEMOYNE)Greenfield345 kV600 MW3.2 yrs64.8
LAKEVIEWSubstation-Adjacent138 kV100 MW3.2 yrs62.7
EC Near Ottawa County ProjectGreenfield3.2 yrs62.4
Greenfield (UNKNOWN114975 - LAKEVIEW)Greenfield138 kV100 MW3.2 yrs61.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Ottawa County Project, Ottawa County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.