Skip to content
Gridcensus

Old Tokio Farmstead

Industrial

Eddy County, North Dakota · SPP

DC Readiness
51.8
Fair / 100

Old Tokio Farmstead is an industrial datacenter candidate site in Eddy County, North Dakota, interconnecting through SPP. It screens at 51.8/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityNORTHERN PLAINS ELECTRIC COOPcooperativefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth15
Avg queue wait3.3 yrs

Connectivity

Nearest IXPMidco Grand Forks
IXP distance94.2 mi
Fiber providers3
Fiber coverage100.0%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score80/100

Location context

Nearest datacenterMidco Grand Forks
DC distance94.2 mi
County hazard (FEMA NRI)Relatively Low (20)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity7.90¢/kWh
Industrial electricity7.94¢/kWh
Cooling degree days500
Heating degree days8,600
Land price / acre$2,088

Regulatory climate

Favorablestate posture · as of 2026-08

Cheap power, land, and cold climate; DC-friendly.

DC tax incentiveYes

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Old Tokio Farmstead

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
51
Fiber connectivity12%
73
Energy cost10%
50
Water risk7%
80
Natural hazard6%
80
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Eddy County, ranked by DC Readiness.

Sites near Old Tokio Farmstead
SiteTypeVoltageCapacityQueue waitScore
BARLOWSubstation-Adjacent115 kV100 MW3.3 yrs57.9
Former Mill Pump PropertyIndustrial——3.3 yrs52.1
Hospital SiteIndustrial——3.3 yrs52.1
Mine SiteFormer Mine——3.3 yrs51.9
Mine SiteFormer Mine——3.3 yrs51.9
Ross Acres Abandoned Home Unit #10Industrial——3.3 yrs51.2
Ross Acres Abandoned Homes Unit #20Industrial——3.3 yrs51.1
Ross Acres burned homesIndustrial——3.3 yrs51.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Old Tokio Farmstead, Eddy County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.