DC Readiness
60.0
Good / 100

EC Coal Warren County is a greenfield datacenter candidate site in Warren County, North Carolina, interconnecting through PJM. It screens at 60.0/100 DC Readiness and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth177
Avg queue wait4.3 yrs
Recent queue wait4.3 yrs
Completion rate14%
Withdrawal rate86%

Connectivity

Nearest IXPLevel(3) Raleigh
IXP distance46.0 mi
Fiber providers6
Fiber coverage57.2%
Nearest cloud providerAzure
Nearest cloud regioneastus2
Cloud region distance15.1 mi

Site characteristics

Site typeGreenfield
Land contactWarren County County Assessor
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score58/100
Construction cost index57.5 (avg 100)

Location context

Nearest datacenterMicrosoft Boydton
DC distance15.0 mi
Nearest rail3.2 mi
Nearest gas pipeline6.8 mi
Nearest fiber route15.4 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.52¢/kWh
Industrial electricity7.87¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$4,721

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
35
Fiber connectivity12%
64
Energy cost10%
94
Water risk8%
85
Natural hazard8%
58
Buildability7%
80
Labor market4%
50
DC cluster4%
95
Land / acreage3%
46
Construction cost3%
100
Gas pipeline2%
78
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Warren County, ranked by DC Readiness.

Sites near EC Coal Warren County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN111420Substation-Adjacent230 kV300 MW3.8 yrs55.0
TAP148055Substation-Adjacent115 kV100 MW3.8 yrs51.4
UNKNOWN111425Substation-Adjacent115 kV100 MW3.8 yrs51.4
TAP148034Substation-Adjacent115 kV100 MW3.8 yrs51.4
UNKNOWN111426Substation-Adjacent115 kV100 MW3.8 yrs51.4
TAP148058Substation-Adjacent115 kV100 MW3.8 yrs51.4
UNKNOWN111429Substation-Adjacent115 kV100 MW3.8 yrs51.4
Peck ManufacturingIndustrial3.8 yrs49.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.