EC Coal Brunswick County

Greenfield

Brunswick County, North Carolina · PJM

DC Readiness
52.4
Fair / 100

EC Coal Brunswick County is a greenfield datacenter candidate site in Brunswick County, North Carolina, interconnecting through PJM. It screens at 52.4/100 DC Readiness and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth177
Avg queue wait4.3 yrs
Recent queue wait4.3 yrs
Completion rate14%
Withdrawal rate86%

Connectivity

Nearest IXPDC BLOX MYR1 - DCBLOX Myrtle Beach
IXP distance64.1 mi
Fiber providers6
Fiber coverage61.0%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance134.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerFunston Land & Timber Llc
Parcel APN0580000758
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score58/100
Construction cost index76.9 (avg 100)

Location context

Nearest datacenterDC BLOX Myrtle Beach Cable Landing Station
DC distance64.2 mi
Nearest rail2.3 mi
Nearest gas pipeline62.6 mi
Nearest fiber route140.7 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.63¢/kWh
Industrial electricity7.87¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$4,930

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
35
Fiber connectivity12%
65
Energy cost10%
94
Water risk8%
84
Natural hazard8%
58
Buildability7%
40
Labor market4%
50
DC cluster4%
25
Land / acreage3%
47
Construction cost3%
86
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Brunswick County, ranked by DC Readiness.

Sites near EC Coal Brunswick County
SiteTypeVoltageCapacityQueue waitScore
TAP148386Substation-Adjacent230 kV300 MW4.3 yrs64.9
TAP148388Substation-Adjacent230 kV300 MW4.3 yrs63.3
UNKNOWN112400Substation-Adjacent230 kV300 MW4.3 yrs63.1
UNKNOWN112410Substation-Adjacent230 kV300 MW4.3 yrs61.8
DELCOSubstation-Adjacent230 kV300 MW4.3 yrs59.0
Greenfield (DELCO - TAP148385)Greenfield230 kV300 MW4.3 yrs58.7
UNKNOWN112406Substation-Adjacent230 kV300 MW4.3 yrs58.3
Greenfield (UNKNOWN112406 - WEATHERSPOON P)Greenfield230 kV300 MW4.3 yrs58.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.