175 River Road

Industrial

Niagara County, New York · NYISO

DC Readiness
52.4
Fair / 100

At a glance

175 River Road is an industrial datacenter candidate site in Niagara County, New York, scoring 52.4/100 DC Readiness — 117th of 237 scored sites in the county. It sits in the NYISO grid region and the NIAGARA MOHAWK POWER CORP. service territory, where interconnection has averaged 4.3 years from request to operation.

Power & interconnection

UtilityNIAGARA MOHAWK POWER CORP.investor ownedmoderate to large load · terms ≥ 20 MW

Speed to power

Interconnection outlookConstrained
≈ 4.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionNYISO
Queue depth95
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate8%
Withdrawal rate92%

Connectivity

Nearest IXPI-Evolve Technology Datacenter Amherst
IXP distance4.8 mi
Fiber providers5
Fiber coverage32.0%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenterFrontier Science
DC distance4.2 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.64¢/kWh
Industrial electricity4.28¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$3,796

Regulatory climate

Restrictivestate posture · as of 2026-08

First statewide moratorium (2026): 1-yr hold on certain permits for large DCs + impact study.

DC tax incentiveNo / suspended
Large-load threshold≥ 50 MW

Moratorium/permit hold targets large datacenters.

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track 175 River Road

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does 175 River Road compare with other sites in Niagara County?

175 River Road ranks 117th of 237 scored candidate sites in Niagara County. Its 52.4/100 is roughly in line with the county average of 53.5. It is roughly in line with the New York average of 54.0 and roughly in line with the national average of 53.2.

Against the New York average, its strongest sub-score is fiber connectivity (80 vs 76) and its weakest is power availability (30 vs 38). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is 175 River Road to power, fiber and other datacenters?

The nearest located transmission bottleneck is BUFALO78 115 HUNTLEY 115 1 (NYISO), 5 miles away. For connectivity, the nearest internet exchange facility is I-Evolve Technology Datacenter Amherst at 4.8 miles. 5 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Frontier Science, 4.2 miles away.

What are the flood, water and hazard risks at 175 River Road?

At the county level, FEMA's National Risk Index rates Niagara County "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
39
Fiber connectivity12%
80
Energy cost10%
50
Water risk7%
90
Natural hazard6%
65
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Niagara County, ranked by DC Readiness.

Sites near 175 River Road
SiteTypeVoltageCapacityQueue waitScore
SOMERSETSubstation-Adjacent345 kV600 MW4.3 yrs63.7
NIAGARASubstation-Adjacent345 kV600 MW4.3 yrs63.6
ROBINSON ROADSubstation-Adjacent230 kV300 MW4.3 yrs63.6
PACKARDSubstation-Adjacent230 kV300 MW4.3 yrs62.8
TAP139815Substation-Adjacent230 kV300 MW4.3 yrs62.7
OZ NiagaraGreenfield——4.3 yrs61.2
UNKNOWN125341Substation-Adjacent115 kV100 MW4.3 yrs59.6
UNKNOWN124205Substation-Adjacent115 kV100 MW4.3 yrs59.5

175 River Road: common questions

What is the DC Readiness score of 175 River Road?

175 River Road scores 52.4/100 on the GridCensus DC Readiness scale, rated fair. It ranks 117th of 237 scored sites in Niagara County. The Niagara County average is 53.5 and the New York average is 54.0.

Which electric utility serves 175 River Road?

NIAGARA MOHAWK POWER CORP. (investor owned) holds the retail service territory that contains the site; its holding company is NATIONAL GRID GROUP PLC.

What grid region is 175 River Road in?

175 River Road is in the NYISO region. Projects interconnecting there have averaged a 4.3-year wait from queue request to operation.

How far is 175 River Road from an internet exchange?

The nearest internet exchange facility is I-Evolve Technology Datacenter Amherst, about 4.8 miles away; 5 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “175 River Road, Niagara County, NY”, https://gridcensus.com/datacenter-sites/new-york/niagara-county/175-river-road-d60d3fcf (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for 175 River Road, Niagara County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.