DUFFY AVENUE CONVERTER STATION is a substation-adjacent datacenter candidate site in Nassau County, New York, interconnecting through NYISO. It screens at 69.8/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 4.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationDUFFY AVENUE CONVERTER STATION
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW
UtilityLONG ISLAND POWER AUTHORITYstate

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionNYISO
Queue depth95
Avg queue wait4.9 yrs

Connectivity

Nearest IXP1025Connect
IXP distance0.5 mi
Fiber providers12
Fiber coverage100.0%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenter1025Connect
DC distance0.5 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity15.40¢/kWh
Industrial electricity27.43¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$62,463

Regulatory climate

Restrictivestate posture · as of 2026-08

First statewide moratorium (2026): 1-yr hold on certain permits for large DCs + impact study.

DC tax incentiveNo / suspended
Large-load threshold≥ 50 MW

Moratorium/permit hold targets large datacenters.

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track DUFFY AVENUE CONVERTER STATION

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power20%
23
Fiber connectivity12%
99
Energy cost10%
50
Water risk7%
90
Natural hazard6%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
100
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Nassau County, ranked by DC Readiness.

Sites near DUFFY AVENUE CONVERTER STATION
SiteTypeVoltageCapacityQueue waitScore
SHORE RDSubstation-Adjacent345 kV600 MW4.9 yrs68.8
EAST GARDEN CITYSubstation-Adjacent345 kV600 MW4.9 yrs67.2
NEWBRIDGE ROADSubstation-Adjacent345 kV600 MW4.9 yrs67.0
EC Near Plant No 2 FreeportGreenfield——3.5 yrs62.1
TAP141012Substation-Adjacent138 kV100 MW4.9 yrs61.2
EC Near Plant No 2 FreeportGreenfield——3.5 yrs61.0
EC Near GlenwoodGreenfield——3.5 yrs61.0
EC Near E F BarrettGreenfield——3.5 yrs61.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for DUFFY AVENUE CONVERTER STATION, Nassau County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.