Datacenter Sites in Genesee County, New York
Genesee County has 47 scored datacenter candidate sites averaging 55.7/100 DC Readiness, with a catalogued aggregate of 9,500 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
47
Candidate sites
55.7/100
Avg DC Readiness
9,500 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Genesee County
Yessales_tax_exemption
Datacenter tax incentive
8.07¢/kWh
Commercial electricity
4.89¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$4,099
Land price / acre
700
Cooling degree days
6,100
Heating degree days
46°F
Mean annual temp
Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
By site type
Top datacenter sites in Genesee County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| SOMERSET | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 66.1 |
| TAP140482 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 64.1 |
| MUMFORD | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 63.4 |
| LAPP | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 63.3 |
| TAP145542 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 62.7 |
| UNKNOWN125171 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 62.6 |
| Greenfield (ROCHESTER #80 - NIAGARA) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 62.3 |
| UNKNOWN124626 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 62.3 |
| TAP155790 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 62.0 |
| TAP155791 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 61.9 |
| Greenfield (ROCHESTER #80 - NIAGARA) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 61.0 |
| TAP145365 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 61.0 |
| Greenfield (ROBINSON ROAD - STOLLE ROAD) | Greenfield | 230 kV | 300 MW | 3.5 yrs | 60.9 |
| E BATAVIA | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.6 |
| Greenfield (ROCHESTER #80 - SOMERSET) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 60.6 |
| TAP140505 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.5 |
| TAP155789 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.3 |
| UNKNOWN125178 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.0 |
| BATAVIA | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 59.6 |
| Greenfield (ROCHESTER #80 - NIAGARA) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 59.4 |
| Greenfield (ROCHESTER #80 - NIAGARA) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 59.4 |
| Greenfield (ROCHESTER #80 - SOMERSET) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 59.2 |
| UNKNOWN124628 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 58.7 |
| Greenfield (ROCHESTER #80 - SOMERSET) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 58.4 |
| Greenfield (ROCHESTER #80 - SOMERSET) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 58.4 |
Genesee County datacenter FAQ
- How many datacenter sites are in Genesee County?
- 47 scored datacenter candidate sites, averaging 55.7/100 DC Readiness.
- Does Genesee County offer datacenter tax incentives?
- Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
- What is the natural-hazard risk in Genesee County?
- FEMA's National Risk Index rates Genesee County as "Relatively High" (score 35).
- What are industrial electricity rates in Genesee County?
- Average industrial electricity is 4.89¢/kWh and commercial is 8.07¢/kWh in Genesee County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Genesee County, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.