Old Gas Station and Convenience Store
IndustrialEsmeralda County, Nevada · WECC
Old Gas Station and Convenience Store is a industrial datacenter candidate site in Esmeralda County, Nevada, interconnecting through WECC. It screens at 39.5/100 DC Readiness.
Power & interconnection
Connectivity
Site characteristics
Risk & environment
Location context
Incentive detail: Partial abatement of sales/use tax and personal property tax for $25M+ DC investments.
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Esmeralda County, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 59.1 |
| ANACONDA | Substation-Adjacent | 230 kV | 300 MW | 5.8 yrs | 56.8 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 56.0 |
| N.O. MILLERS | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 54.1 |
| TONOPAH | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 53.1 |
| SILVER PEAK | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 52.7 |
| BLM Solar DLA: Millers | Greenfield | — | 4,467 MW | 5.8 yrs | 51.4 |
| Greenfield (UNKNOWN305563 - ANACONDA) | Greenfield | 230 kV | 300 MW | 5.8 yrs | 51.4 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Old Gas Station and Convenience Store, Esmeralda County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.