Skip to content
Gridcensus

Leach's Radiator Shop

Industrial

Gage County, Nebraska · SPP

DC Readiness
50.9
Fair / 100

Leach's Radiator Shop is an industrial datacenter candidate site in Gage County, Nebraska, interconnecting through SPP. It screens at 50.9/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest grid bottleneckTMP918_33023 · 90 km (SPP)
UtilityNORRIS PUBLIC POWER DISTRICTpolitical subdivisionfavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth27
Avg queue wait3.3 yrs

Connectivity

Nearest IXPLincoln Data Centers
IXP distance37.8 mi
Fiber providers10
Fiber coverage85.6%

Site characteristics

Site typeIndustrial
Land contactGage County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterLincoln Data Centers
DC distance37.8 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.99¢/kWh
Industrial electricity6.54¢/kWh
Cooling degree days1,000
Heating degree days6,200
Land price / acre$5,474

Regulatory climate

Favorablestate posture · as of 2026-08

Public-power incentives; DC-friendly.

DC tax incentiveYes

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Leach's Radiator Shop

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
52
Fiber connectivity12%
74
Energy cost10%
50
Water risk7%
60
Natural hazard6%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
50
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Gage County, ranked by DC Readiness.

Sites near Leach's Radiator Shop
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN131689Substation-Adjacent115 kV100 MW3.3 yrs56.8
UNKNOWN131699Substation-Adjacent115 kV100 MW3.3 yrs56.7
UNKNOWN131686Substation-Adjacent115 kV100 MW3.3 yrs56.7
Village of AdamsIndustrial——3.3 yrs51.9
Greenfield (UNKNOWN131684 - BEATRICE)Greenfield115 kV100 MW3.3 yrs51.3
Farmers Union Co-op SupplyIndustrial——3.3 yrs50.9
Store Kraft ManufacturingIndustrial——3.3 yrs50.9
Hickory Industrial ParkIndustrial——3.3 yrs50.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Leach's Radiator Shop, Gage County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.