RICHARDSON COULEE

Substation-Adjacent

Valley County, Montana · SPP

DC Readiness
61.2
Good / 100

RICHARDSON COULEE is a substation-adjacent datacenter candidate site in Valley County, Montana, interconnecting through SPP. It screens at 61.2/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationRICHARDSON COULEE
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
UtilityNORVAL ELECTRIC COOPERATIVE, INCnot availablefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth35
Avg queue wait3.3 yrs

Connectivity

Fiber providers1
Fiber coverage60.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score88/100

Location context

Nearest datacenterState of Montana Data Center
DC distance133.8 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity8.83¢/kWh
Industrial electricity6.16¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$1,152

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: New/expanding industry tax abatement available for DC construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track RICHARDSON COULEE

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power20%
56
Fiber connectivity12%
66
Energy cost10%
50
Water risk7%
56
Natural hazard6%
88
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
54
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Valley County, ranked by DC Readiness.

Sites near RICHARDSON COULEE
SiteTypeVoltageCapacityQueue waitScore
FORT PECKSubstation-Adjacent230 kV300 MW3.3 yrs60.4
UNKNOWN204560Substation-Adjacent115 kV100 MW3.3 yrs57.0
UNKNOWN205525Substation-Adjacent115 kV100 MW3.3 yrs56.9
UNKNOWN205516Substation-Adjacent115 kV100 MW3.3 yrs56.3
UNKNOWN205522Substation-Adjacent115 kV100 MW3.3 yrs56.3
TAP205523Substation-Adjacent115 kV100 MW3.3 yrs55.9
UNKNOWN205524Substation-Adjacent115 kV100 MW3.3 yrs55.8
TAP205520Substation-Adjacent115 kV100 MW3.3 yrs55.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.