Skip to content
Gridcensus

Withdrawn Land Region6-GP

Federal Excess

McCone County, Montana · MISO

DC Readiness
48.7
Fair / 100

Withdrawn Land Region6-GP is a federal excess datacenter candidate site in McCone County, Montana, interconnecting through MISO. It screens at 48.7/100 DC Readiness and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

UtilitySHERIDAN ELECTRIC COOP, INCnot availablefavorable to large load · state default

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth170
Avg queue wait2.8 yrs

Connectivity

Fiber providers2
Fiber coverage63.9%

Site characteristics

Acreage37 ac
Buildable load (est.)~15–37 MWland-based
Land contactMcCone County County Assessor
Former useReclamation and Irrigation

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score88/100

Location context

Nearest datacenterState of Montana Data Center
DC distance119.0 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity11.68¢/kWh
Industrial electricity8.92¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$1,055

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: New/expanding industry tax abatement available for DC construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Withdrawn Land Region6-GP

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
45
Fiber connectivity12%
67
Energy cost10%
50
Water risk7%
56
Natural hazard6%
88
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
50
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in McCone County, ranked by DC Readiness.

Sites near Withdrawn Land Region6-GP
SiteTypeVoltageCapacityQueue waitScore
WOLF POINTSubstation-Adjacent230 kV300 MW3.3 yrs61.5
UNKNOWN202118Substation-Adjacent138 kV100 MW3.3 yrs57.1
UNKNOWN204630Substation-Adjacent115 kV100 MW3.3 yrs56.0
TAP208288Substation-Adjacent69 kV50 MW3.3 yrs55.2
CIRCLE #1Substation-Adjacent69 kV50 MW3.3 yrs55.0
UNKNOWN208285Substation-Adjacent69 kV50 MW3.3 yrs54.8
TAP208284Substation-Adjacent69 kV50 MW3.3 yrs54.8
UNKNOWN208283Substation-Adjacent69 kV50 MW3.3 yrs54.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.