Skip to content
Gridcensus

Pleasant View Apartments

Industrial

Carbon County, Montana · SPP

DC Readiness
54.2
Fair / 100

Pleasant View Apartments is an industrial datacenter candidate site in Carbon County, Montana, interconnecting through SPP. It screens at 54.2/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait3.3 yrs

Connectivity

Nearest IXPParsec
IXP distance25.2 mi
Fiber providers4
Fiber coverage15.2%

Site characteristics

Site typeIndustrial

Risk & environment

Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score88/100

Location context

Nearest datacenterParsec
DC distance25.2 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity8.82¢/kWh
Industrial electricity6.59¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$1,923

Incentive detail: New/expanding industry tax abatement available for DC construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
66
Fiber connectivity12%
55
Energy cost10%
50
Water risk8%
56
Natural hazard8%
88
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
54
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Carbon County, ranked by DC Readiness.

Sites near Pleasant View Apartments
SiteTypeVoltageCapacityQueue waitScore
OZ CarbonGreenfield1.1 yrs60.4
TAP206174Substation-Adjacent69 kV50 MW3.3 yrs57.9
UNKNOWN206175Substation-Adjacent69 kV50 MW3.3 yrs57.6
UNKNOWN206179Substation-Adjacent115 kV100 MW3.3 yrs57.3
TAP206178Substation-Adjacent115 kV100 MW3.3 yrs57.2
UNKNOWN206173Substation-Adjacent69 kV50 MW3.3 yrs56.5
Mine SiteFormer Mine3.3 yrs55.5
UNKNOWN206172Substation-Adjacent69 kV50 MW3.3 yrs55.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Pleasant View Apartments, Carbon County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.