Miller Property

Industrial

Blaine County, Montana · SPP

DC Readiness
53.8
Fair / 100

Miller Property is an industrial datacenter candidate site in Blaine County, Montana, interconnecting through SPP. It screens at 53.8/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityNORTHWESTERN ENERGY LLC - (MT)investor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth1
Avg queue wait3.3 yrs

Connectivity

Fiber providers3
Fiber coverage95.9%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score88/100

Location context

County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity8.26¢/kWh
Industrial electricity6.91¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$849

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: New/expanding industry tax abatement available for DC construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Miller Property

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
58
Fiber connectivity12%
77
Energy cost10%
50
Water risk7%
56
Natural hazard6%
88
Buildability7%
50
Labor market4%
50
DC cluster4%
10
Land / acreage3%
54
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Blaine County, ranked by DC Readiness.

Sites near Miller Property
SiteTypeVoltageCapacityQueue waitScore
OZ BlaineGreenfield——1.1 yrs65.1
HARLEMSubstation-Adjacent230 kV300 MW3.3 yrs64.0
CHINOOKSubstation-Adjacent69 kV50 MW3.3 yrs57.7
UNKNOWN208255Substation-Adjacent69 kV50 MW3.3 yrs57.7
UNKNOWN208250Substation-Adjacent69 kV50 MW3.3 yrs57.6
UNKNOWN208261Substation-Adjacent69 kV50 MW3.3 yrs57.5
UNKNOWN208263Substation-Adjacent69 kV50 MW3.3 yrs57.4
UNKNOWN208256Substation-Adjacent69 kV50 MW3.3 yrs57.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Miller Property, Blaine County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.