EC Coal Pike County

Greenfield

Pike County, Missouri · MISO

DC Readiness
53.2
Fair / 100

EC Coal Pike County is a greenfield datacenter candidate site in Pike County, Missouri, interconnecting through MISO. It screens at 53.2/100 DC Readiness and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth34
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPTierPoint St. Louis – Millpark
IXP distance49.1 mi
Fiber providers3
Fiber coverage49.8%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance212.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerUNION ELECTRIC CO - (MO)
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score62/100
Construction cost index82.9 (avg 100)

Location context

Nearest datacenterTierPoint St. Louis – Millpark
DC distance49.1 mi
Nearest rail3.3 mi
Nearest gas pipeline11.7 mi
Nearest fiber route226.6 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.61¢/kWh
Industrial electricity8.16¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$4,561

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
48
Fiber connectivity12%
18
Energy cost10%
89
Water risk8%
88
Natural hazard8%
62
Buildability7%
75
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
81
Gas pipeline2%
62
Tax incentive2%
100
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Pike County, ranked by DC Readiness.

Sites near EC Coal Pike County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN117928Substation-Adjacent161 kV100 MW4.6 yrs64.5
UNKNOWN117751Substation-Adjacent161 kV100 MW4.6 yrs64.2
PENO CREEKSubstation-Adjacent161 kV100 MW4.6 yrs62.8
TAP140538Substation-Adjacent161 kV100 MW4.6 yrs60.9
UNKNOWN117876Substation-Adjacent161 kV100 MW4.6 yrs60.4
TAP140539Substation-Adjacent161 kV100 MW4.6 yrs58.9
EC Coal Pike CountyGreenfield1.4 yrs58.2
Greenfield (TAP139400 - TAP140540)Greenfield161 kV100 MW4.6 yrs57.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Pike County, Pike County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.