Datacenter Sites in ADAMS, Mississippi
ADAMS has 42 scored datacenter candidate sites averaging 51.7/100 DC Readiness, with a catalogued aggregate of 1,266 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
42
Candidate sites
51.7/100
Avg DC Readiness
1,266 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for ADAMS
Yessales_tax_exemption
Datacenter tax incentive
13.16¢/kWh
Commercial electricity
8.96¢/kWh
Industrial electricity
3
Fiber providers
Low
Water stress
$3,265
Land price / acre
2,400
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
By site type
Top datacenter sites in ADAMS
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN110662 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.7 |
| UNKNOWN110664 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.5 |
| TAP142768 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.1 |
| UNKNOWN110660 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.9 |
| UNKNOWN166929 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.0 |
| TAP142912 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 61.4 |
| UNKNOWN115941 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 61.0 |
| NATCHEZ | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 60.7 |
| UNKNOWN169435 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 60.3 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 57.2 |
| UNKNOWN115946 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 57.1 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 56.9 |
| Natchez | Brownfield | — | 66 MW | 1.4 yrs | 56.8 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 56.7 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 56.5 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 56.3 |
| EC FFE Adams County | Greenfield | — | — | 1.4 yrs | 56.1 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 55.2 |
| Greenfield (TAP142912 - TAP142946) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 53.5 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 52.5 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 52.5 |
| OZ Adams | Greenfield | — | — | 1.4 yrs | 51.5 |
| EC Near Natchez | Greenfield | — | — | 1.4 yrs | 50.9 |
| Greenfield (TAP142912 - TAP142946) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 50.7 |
| ST. CATHERINE READY-MIX, INC. (READY-MIX CONCRETE MANUFACTURING) | Manufacturing | — | — | — | 45.4 |
ADAMS datacenter FAQ
- How many datacenter sites are in ADAMS?
- 42 scored datacenter candidate sites, averaging 51.7/100 DC Readiness.
- Does ADAMS offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
- What is the natural-hazard risk in ADAMS?
- FEMA's National Risk Index rates ADAMS as "Relatively High" (score 45).
- What are industrial electricity rates in ADAMS?
- Average industrial electricity is 8.96¢/kWh and commercial is 13.16¢/kWh in ADAMS.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen