OZ Wabasha

Greenfield

Wabasha County, Minnesota · MISO

DC Readiness
52.8
Fair / 100

OZ Wabasha is a greenfield datacenter candidate site in Wabasha County, Minnesota, interconnecting through MISO. It screens at 52.8/100 DC Readiness and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPSFN MN-Rochester
IXP distance30.7 mi
Fiber providers5
Fiber coverage59.1%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance182.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerDAIRYLAND POWER COOPERATIVE
Land owner typeprivate
Buildability5.0/100
Land cover (NLCD)Water

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyPresent
Superfund sitePEPIN MANUFACTURING INC
Hazard sub-score55/100
Construction cost index58.7 (avg 100)

Location context

Nearest datacenterEpic / Mayo Data Center
DC distance28.8 mi
Nearest rail1.1 mi
Nearest gas pipeline3.1 mi
Nearest fiber route171.0 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.36¢/kWh
Industrial electricity10.22¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$6,636

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
57
Fiber connectivity12%
22
Energy cost10%
86
Water risk8%
89
Natural hazard8%
55
Buildability7%
5
Labor market4%
50
DC cluster4%
65
Land / acreage3%
59
Construction cost3%
100
Gas pipeline2%
90
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Wabasha County, ranked by DC Readiness.

Sites near OZ Wabasha
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN129279Substation-Adjacent161 kV100 MW1.4 yrs72.5
Greenfield (NORTH ROCHESTER - BRIGGS ROAD)Greenfield345 kV600 MW1.4 yrs70.9
Greenfield (NORTH ROCHESTER - BRIGGS ROAD)Greenfield345 kV600 MW1.4 yrs70.4
Greenfield (NORTH ROCHESTER - BRIGGS ROAD)Greenfield345 kV600 MW1.4 yrs69.9
Greenfield (NORTH ROCHESTER - BRIGGS ROAD)Greenfield345 kV600 MW1.4 yrs63.3
EC Coal Wabasha CountyGreenfield1.4 yrs62.4
EC Coal Wabasha CountyGreenfield1.4 yrs61.8
Greenfield (UNKNOWN129279 - ALMA)Greenfield161 kV100 MW1.4 yrs60.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.