Greenfield (UNKNOWN130180 - UNKNOWN134608)

Greenfield

Traill County, Minnesota · MISO

DC Readiness
53.0
Fair / 100

Greenfield (UNKNOWN130180 - UNKNOWN134608) is a greenfield datacenter candidate site in Traill County, Minnesota, interconnecting through MISO. It screens at 53.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN130180
Substation voltage115 kV
Available capacity100 MW
UtilityNORTHERN STATES POWER CO - MINNESOTAinvestor ownedmoderate to large load · terms ≥ 100 MWMinnesota large-load statute (2025): DCs pay own costs, no cross-subsidy

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth127
Avg queue wait2.8 yrs

Connectivity

Nearest IXPMidco Grand Forks
IXP distance13.7 mi
Fiber providers5
Fiber coverage58.8%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score80/100

Location context

Nearest datacenterMidco Grand Forks
DC distance13.7 mi
County hazard (FEMA NRI)Relatively Low (20)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity6.44¢/kWh
Industrial electricity8.49¢/kWh
Cooling degree days500
Heating degree days8,600
Land price / acre$3,725

Regulatory climate

Moderatestate posture · as of 2026-08

Incentives available; large-load tariffs emerging.

DC tax incentiveYes
Large-load threshold≥ 50 MW

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (UNKNOWN130180 - UNKNOWN134608)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power20%
45
Fiber connectivity12%
76
Energy cost10%
50
Water risk7%
80
Natural hazard6%
80
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Traill County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN130180 - UNKNOWN134608)
SiteTypeVoltageCapacityQueue waitScore
TAP161693Substation-Adjacent69 kV50 MW3.3 yrs59.1
TAP161694Substation-Adjacent69 kV50 MW3.3 yrs58.7
UNKNOWN134587Substation-Adjacent69 kV50 MW3.3 yrs58.6
UNKNOWN134610Substation-Adjacent69 kV50 MW3.3 yrs58.0
UNKNOWN134608Substation-Adjacent115 kV100 MW3.3 yrs57.4
UNKNOWN134583Substation-Adjacent69 kV50 MW3.3 yrs57.4
UNKNOWN134605Substation-Adjacent69 kV50 MW3.3 yrs57.1
UNKNOWN134609Substation-Adjacent69 kV50 MW3.3 yrs56.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN130180 - UNKNOWN134608), Traill County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.