Silvermark

Industrial

Hennepin County, Minnesota · MISO

DC Readiness
55.4
Good / 100

At a glance

Silvermark is an industrial datacenter candidate site in Hennepin County, Minnesota, scoring 55.4/100 DC Readiness — 214th of 237 scored sites in the county. It sits in the MISO grid region and the NORTHERN STATES POWER CO - MINNESOTA service territory, where interconnection has averaged 4.3 years from request to operation.

Power & interconnection

UtilityNORTHERN STATES POWER CO - MINNESOTAinvestor ownedmoderate to large load · terms ≥ 100 MWMinnesota large-load statute (2025): DCs pay own costs, no cross-subsidy

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth127
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPT5@Minneapolis
IXP distance1.2 mi
Fiber providers19
Fiber coverage72.8%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterT5@Minneapolis
DC distance1.2 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.60¢/kWh
Industrial electricity9.85¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$17,237

Regulatory climate

Moderatestate posture · as of 2026-08

Incentives available; large-load tariffs emerging.

DC tax incentiveYes
Large-load threshold≥ 50 MW

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Silvermark

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Silvermark compare with other sites in Hennepin County?

Silvermark ranks 214th of 237 scored candidate sites in Hennepin County. Its 55.4/100 is roughly in line with the county average of 57.7. It is roughly in line with the Minnesota average of 55.7 and roughly in line with the national average of 53.2.

Against the Minnesota average, its strongest sub-score is fiber connectivity (78 vs 70) and its weakest is power availability (30 vs 39). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Silvermark to power, fiber and other datacenters?

The nearest located transmission bottleneck is West_Memphis_AT1_161_500kV_flo_Sans_Souci_Driver (MISO), 64 miles away. For connectivity, the nearest internet exchange facility is T5@Minneapolis at 1.2 miles. 19 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is T5@Minneapolis, 1.2 miles away.

What are the flood, water and hazard risks at Silvermark?

The site is in FEMA flood zone X, outside the Special Flood Hazard Area (minimal or moderate flood risk). At the county level, FEMA's National Risk Index rates Hennepin County "Relatively Moderate".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
48
Fiber connectivity12%
78
Energy cost10%
50
Water risk7%
92
Natural hazard6%
75
Buildability7%
50
Labor market4%
50
DC cluster4%
100
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
95

Nearby comparable sites

Other scored datacenter candidate sites in Hennepin County, ranked by DC Readiness.

Sites near Silvermark
SiteTypeVoltageCapacityQueue waitScore
PARKERS LAKESubstation-Adjacent345 kV600 MW4.3 yrs69.5
EDEN PRAIRIESubstation-Adjacent345 kV600 MW4.3 yrs69.4
UNKNOWN129614Substation-Adjacent345 kV600 MW4.3 yrs68.5
EC Near Alliant TechsystemsGreenfield——4.3 yrs64.8
EC Near Riverside (MN)Greenfield——4.3 yrs64.4
EC Near Riverside (MN)Greenfield——4.3 yrs64.3
OZ HennepinGreenfield——4.3 yrs64.0
EC Near Riverside (MN)Greenfield——4.3 yrs63.9

Silvermark: common questions

What is the DC Readiness score of Silvermark?

Silvermark scores 55.4/100 on the GridCensus DC Readiness scale, rated good. It ranks 214th of 237 scored sites in Hennepin County. The Hennepin County average is 57.7 and the Minnesota average is 55.7.

Which electric utility serves Silvermark?

NORTHERN STATES POWER CO - MINNESOTA (investor owned) holds the retail service territory that contains the site; its holding company is XCEL ENERGY INC.

What grid region is Silvermark in?

Silvermark is in the MISO region. Projects interconnecting there have averaged a 4.3-year wait from queue request to operation.

Is Silvermark in a flood zone?

The site is in FEMA flood zone X, outside the Special Flood Hazard Area (minimal or moderate flood risk).

How far is Silvermark from an internet exchange?

The nearest internet exchange facility is T5@Minneapolis, about 1.2 miles away; 19 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Silvermark, Hennepin County, MN”, https://gridcensus.com/datacenter-sites/minnesota/hennepin-county/silvermark-0168f11d (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Silvermark, Hennepin County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.