Big Spring Inn

Industrial

Schoolcraft County, Michigan · MISO

DC Readiness
51.7
Fair / 100

Big Spring Inn is an industrial datacenter candidate site in Schoolcraft County, Michigan, interconnecting through MISO. It screens at 51.7/100 DC Readiness and a 2.2 yrs average interconnection-queue wait.

Power & interconnection

UtilityUPPER PENINSULA POWER COMPANYinvestor ownedfavorable to large load · terms ≥ 100 MW

Speed to power

Interconnection outlookFavorable
≈ 2.2 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth286
Avg queue wait2.2 yrs
Recent queue wait2.2 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPMI Tech - Main Campus
IXP distance128.7 mi
Fiber providers5
Fiber coverage59.0%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterMI Tech - Main Campus
DC distance128.7 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity14.37¢/kWh
Industrial electricity8.17¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$2,839

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Big Spring Inn

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
54
Fiber connectivity12%
63
Energy cost10%
50
Water risk7%
94
Natural hazard6%
75
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Schoolcraft County, ranked by DC Readiness.

Sites near Big Spring Inn
SiteTypeVoltageCapacityQueue waitScore
OZ SchoolcraftGreenfield——2.2 yrs59.6
INDIAN LAKESubstation-Adjacent138 kV100 MW2.2 yrs58.4
GARDEN CORNERSSubstation-Adjacent138 kV100 MW2.2 yrs58.4
BLANEY PARK SW STASubstation-Adjacent138 kV100 MW2.2 yrs58.2
TAP171615Substation-Adjacent69 kV50 MW2.2 yrs56.1
MANISTIQUESubstation-Adjacent69 kV50 MW2.2 yrs56.1
EC FFE Schoolcraft CountyGreenfield——2.2 yrs54.2
Mine SiteFormer Mine——2.2 yrs52.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Big Spring Inn, Schoolcraft County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.