Skip to content
Gridcensus

Luce County, Michigan · PJM

DC Readiness
53.3
Fair / 100

TAP171269 is a substation-adjacent datacenter candidate site in Luce County, Michigan, interconnecting through PJM. It screens at 53.3/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP171269
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityCLOVERLAND ELECTRIC CO-OPcooperativefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth17
Avg queue wait3.8 yrs

Connectivity

Fiber providers4
Fiber coverage82.1%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score75/100

Location context

County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity14.12¢/kWh
Industrial electricity10.69¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$3,109

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 7 nearby

Get alerts

Track TAP171269

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
37
Fiber connectivity12%
75
Energy cost10%
50
Water risk7%
94
Natural hazard6%
75
Buildability7%
60
Labor market4%
50
DC cluster4%
10
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Luce County, ranked by DC Readiness.

Sites near TAP171269
SiteTypeVoltageCapacityQueue waitScore
NEWBERRY VLGSubstation-Adjacent69 kV50 MW3.8 yrs53.3
ROBERTS SW STASubstation-Adjacent69 kV50 MW3.8 yrs53.3
SENEY (AD-REA)Substation-Adjacent69 kV50 MW3.8 yrs53.2
NEWBERRYSubstation-Adjacent69 kV50 MW3.8 yrs53.1
OZ LuceGreenfield2.2 yrs51.7
Old Charcoal Iron PropertyIndustrial3.8 yrs49.4
EC FFE Luce CountyGreenfield2.2 yrs45.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP171269, Luce County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.