Datacenter Sites in Franklin County, Massachusetts
Franklin County has 133 scored datacenter candidate sites averaging 44.1/100 DC Readiness, with a catalogued aggregate of 7,414 MW. FEMA rates local natural-hazard risk as "Relatively Low".
133
Candidate sites
44.1/100
Avg DC Readiness
7,414 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Franklin County
No
Datacenter tax incentive
16.57¢/kWh
Commercial electricity
16.32¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$8,637
Land price / acre
600
Cooling degree days
5,900
Heating degree days
49°F
Mean annual temp
By site type
Top datacenter sites in Franklin County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| AMHERST | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 64.8 |
| VERMONT YANKEE | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 62.9 |
| NORTHFIELD | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 62.6 |
| BEAR SWAMP | Substation-Adjacent | 230 kV | 300 MW | 3.5 yrs | 60.5 |
| MONTAGUE/CABOT | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 57.1 |
| Greenfield (BERKSHIRE - NORTHFIELD) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 56.8 |
| Greenfield (EASTOVER - BEAR SWAMP) | Greenfield | 230 kV | 300 MW | 3.5 yrs | 56.6 |
| UNKNOWN172513 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 56.6 |
| UNKNOWN157942 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 55.9 |
| TAP135873 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 55.6 |
| Greenfield (BERKSHIRE - NORTHFIELD) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 55.5 |
| Greenfield (PRATTS JUNCTION - BEAR SWAMP) | Greenfield | 230 kV | 300 MW | 3.5 yrs | 55.0 |
| TAP161086 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 54.9 |
| Greenfield (PRATTS JUNCTION - BEAR SWAMP) | Greenfield | 230 kV | 300 MW | 3.5 yrs | 54.8 |
| Greenfield (VERNON VT - NORTHFIELD) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 54.3 |
| PODICK | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 54.2 |
| Greenfield (PRATTS JUNCTION - BEAR SWAMP) | Greenfield | 230 kV | 300 MW | 3.5 yrs | 54.1 |
| Greenfield Solar Farm | Brownfield | — | 2 MW | — | 53.5 |
| ASHFIELD | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 53.5 |
| EC Near Erving Paper Mills | Greenfield | — | — | 3.5 yrs | 53.4 |
| TAP135582 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 53.3 |
| OZ Franklin | Greenfield | — | — | 3.5 yrs | 52.9 |
| TAP155822 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 52.8 |
| EC Near Erving Paper Mills | Greenfield | — | — | 3.5 yrs | 52.2 |
| Erving Paper Mills | Brownfield | — | 3 MW | 3.5 yrs | 51.9 |
Franklin County datacenter FAQ
- How many datacenter sites are in Franklin County?
- 133 scored datacenter candidate sites, averaging 44.1/100 DC Readiness.
- Does Franklin County offer datacenter tax incentives?
- No datacenter-specific tax incentive is on record for Franklin County in our dataset.
- What is the natural-hazard risk in Franklin County?
- FEMA's National Risk Index rates Franklin County as "Relatively Low" (score 22).
- What are industrial electricity rates in Franklin County?
- Average industrial electricity is 16.32¢/kWh and commercial is 16.57¢/kWh in Franklin County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Franklin County, Massachusetts. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.