EC Near D G Hunter

Greenfield

Rapides County, Louisiana · MISO

DC Readiness
48.5
Fair / 100

EC Near D G Hunter is a greenfield datacenter candidate site in Rapides County, Louisiana, interconnecting through MISO. It screens at 48.5/100 DC Readiness and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneMISO_LOUISIANA
Wholesale LMP$32.39/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth53
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPVenyu BTR1
IXP distance93.7 mi
Fiber providers8
Fiber coverage47.3%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance278.8 mi

Site characteristics

Site typeGreenfield
Land contactRapides County Assessor
Land owner typeprivate
Buildability50.0/100
Former usenear retired gas plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score42/100
Construction cost index97.8 (avg 100)

Location context

Nearest datacenterCenter for Computation & Technology (CCT)
DC distance93.0 mi
Nearest rail1.6 mi
Nearest gas pipeline0.2 mi
Nearest fiber route165.3 mi
County hazard (FEMA NRI)Very High (58)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.70¢/kWh
Industrial electricity8.12¢/kWh
Cooling degree days2,700
Heating degree days1,700
Land price / acre$3,817

Incentive detail: Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
48
Fiber connectivity12%
19
Energy cost10%
88
Water risk8%
87
Natural hazard8%
42
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
48
Construction cost3%
69
Gas pipeline2%
99
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Rapides County, ranked by DC Readiness.

Sites near EC Near D G Hunter
SiteTypeVoltageCapacityQueue waitScore
EC Near D G HunterGreenfield1.4 yrs55.3
EC Near D G HunterGreenfield1.4 yrs54.9
EC Near D G HunterGreenfield1.4 yrs54.6
RAPIDESSubstation-Adjacent230 kV300 MW2.8 yrs52.4
UNKNOWN112590Substation-Adjacent230 kV300 MW2.8 yrs52.4
FOREST HILLSubstation-Adjacent230 kV300 MW2.8 yrs52.4
UNKNOWN116379Substation-Adjacent230 kV300 MW2.8 yrs52.4
UNKNOWN115952Substation-Adjacent230 kV300 MW2.8 yrs52.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near D G Hunter, Rapides County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.