WILLOW GLEN (500KV)

Substation-Adjacent

Ascension Parish, Louisiana · MISO

DC Readiness
71.7
Excellent / 100

WILLOW GLEN (500KV) is a substation-adjacent datacenter candidate site in Ascension Parish, Louisiana, interconnecting through MISO. It screens at 71.7/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWILLOW GLEN (500KV)
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW
UtilityENTERGY LOUISIANA LLCinvestor ownedfavorable to large load · terms ≥ 50 MWLarge-load contracts with dedicated generation (Meta Richland Parish) · 15 yr

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth120
Avg queue wait2.8 yrs

Connectivity

Nearest IXPDartPoints Baton Rouge, LA - BTR1
IXP distance12.0 mi
Fiber providers4
Fiber coverage94.7%

Site characteristics

Former usegas
Existing capacity2,178 MW
Retirement date2018-03-01

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score42/100

Location context

Nearest datacenterCenter for Computation & Technology (CCT)
DC distance9.6 mi
County hazard (FEMA NRI)Very High (58)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.02¢/kWh
Industrial electricity9.11¢/kWh
Cooling degree days2,700
Heating degree days1,700
Land price / acre$5,985

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track WILLOW GLEN (500KV)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power20%
69
Fiber connectivity12%
89
Energy cost10%
50
Water risk7%
88
Natural hazard6%
42
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Ascension Parish, ranked by DC Readiness.

Sites near WILLOW GLEN (500KV)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN115491Substation-Adjacent230 kV300 MW2.8 yrs63.2
UNKNOWN112511Substation-Adjacent230 kV300 MW2.8 yrs63.2
UNKNOWN115481Substation-Adjacent230 kV300 MW2.8 yrs63.1
UNKNOWN112514Substation-Adjacent230 kV300 MW2.8 yrs63.0
UNKNOWN111923Substation-Adjacent230 kV300 MW2.8 yrs62.9
UNKNOWN115489Substation-Adjacent230 kV300 MW2.8 yrs61.9
UNKNOWN112507Substation-Adjacent230 kV300 MW2.8 yrs61.9
UNKNOWN161921Substation-Adjacent230 kV300 MW2.8 yrs61.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for WILLOW GLEN (500KV), Ascension Parish. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.