EC Near Mason County LFGTE

Greenfield

Mason, Kentucky · PJM

DC Readiness
57.0
Good / 100

EC Near Mason County LFGTE is a greenfield datacenter candidate site in Mason, Kentucky, interconnecting through PJM. It screens at 57.0/100 DC Readiness and a 3.6 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth221
Avg queue wait3.6 yrs
Recent queue wait4.7 yrs
Completion rate7%
Withdrawal rate93%

Connectivity

Nearest IXPLevel(3) Cincinnati
IXP distance55.9 mi
Fiber providers3
Fiber coverage59.5%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance97.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerEAST KENTUCKY POWER COOP, INC
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest
Former usenear retired gas plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index91.0 (avg 100)

Location context

Nearest datacenterLevel(3) Cincinnati
DC distance55.9 mi
Nearest rail1.6 mi
Nearest gas pipeline4.0 mi
Nearest fiber route41.3 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.18¢/kWh
Industrial electricity6.77¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$4,053

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
37
Fiber connectivity12%
65
Energy cost10%
93
Water risk8%
90
Natural hazard8%
70
Buildability7%
45
Labor market4%
50
DC cluster4%
45
Land / acreage3%
49
Construction cost3%
74
Gas pipeline2%
87
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Mason, ranked by DC Readiness.

Sites near EC Near Mason County LFGTE
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN121396Substation-Adjacent345 kV600 MW3.2 yrs68.0
UNKNOWN121394Substation-Adjacent138 kV100 MW3.2 yrs66.8
UNKNOWN121397Substation-Adjacent138 kV100 MW3.2 yrs65.7
Greenfield (J M STUART - ATLANTA)Greenfield345 kV600 MW3.2 yrs65.1
Greenfield (J M STUART - UNKNOWN121396)Greenfield345 kV600 MW3.2 yrs65.0
UNKNOWN121395Substation-Adjacent138 kV100 MW3.2 yrs64.8
TAP137338Substation-Adjacent138 kV100 MW3.2 yrs64.7
Greenfield (J M STUART - UNKNOWN113907)Greenfield345 kV600 MW3.2 yrs63.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Mason County LFGTE, Mason. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.