Greenfield (UNKNOWN122681 - TAP155985)

Greenfield

Caldwell County, Kentucky · PJM

DC Readiness
48.0
Fair / 100

Greenfield (UNKNOWN122681 - TAP155985) is a greenfield datacenter candidate site in Caldwell County, Kentucky, interconnecting through PJM. It screens at 48.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN122681
Substation voltage161 kV
Available capacity100 MW
UtilityKENERGY CORPcooperativefavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth175
Avg queue wait3.8 yrs

Connectivity

Nearest IXPEnergynet Datacenter
IXP distance37.7 mi
Fiber providers4
Fiber coverage18.4%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterDynamics Mining
DC distance15.6 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.06¢/kWh
Industrial electricity6.36¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$4,783

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (UNKNOWN122681 - TAP155985)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
32
Speed to power20%
37
Fiber connectivity12%
49
Energy cost10%
50
Water risk7%
92
Natural hazard6%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
47
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
60

Nearby comparable sites

Other scored datacenter candidate sites in Caldwell County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN122681 - TAP155985)
SiteTypeVoltageCapacityQueue waitScore
EC FFE Caldwell CountyGreenfield3.6 yrs56.6
TAP122968Substation-Adjacent161 kV100 MW3.8 yrs55.2
TAP169241Substation-Adjacent161 kV100 MW3.8 yrs55.2
UNKNOWN169243Substation-Adjacent161 kV100 MW3.8 yrs55.1
UNKNOWN122970Substation-Adjacent161 kV100 MW3.8 yrs54.8
EC Coal Caldwell CountyGreenfield3.6 yrs54.4
TAP155985Substation-Adjacent161 kV100 MW3.8 yrs54.3
UNKNOWN123323Substation-Adjacent69 kV50 MW3.8 yrs53.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN122681 - TAP155985), Caldwell County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.