TAP140589 is a substation-adjacent datacenter candidate site in Finney County, Kansas, interconnecting through SPP. It screens at 52.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP140589
Nearest grid bottleneckCIMXF2CIMXF3 · 46 km (SPP)
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
UtilityWHEATLAND ELECTRIC COOP, INCcooperativefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth59
Avg queue wait3.3 yrs

Connectivity

Fiber providers6
Fiber coverage77.4%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenterCloud Storage Corp
DC distance108.0 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity10.15¢/kWh
Industrial electricity8.46¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$2,333

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track TAP140589

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power20%
33
Fiber connectivity12%
71
Energy cost10%
50
Water risk7%
52
Natural hazard6%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
55

Nearby comparable sites

Other scored datacenter candidate sites in Finney County, ranked by DC Readiness.

Sites near TAP140589
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN209699Substation-Adjacent345 kV600 MW3.3 yrs59.0
HOLCOMBSubstation-Adjacent345 kV600 MW3.3 yrs59.0
OZ FinneyGreenfield——3.5 yrs56.8
EC Near Garden CityGreenfield——3.5 yrs55.6
EC Near Garden CityGreenfield——3.5 yrs55.3
EC Near Garden CityGreenfield——3.5 yrs54.5
UNKNOWN119612Substation-Adjacent115 kV100 MW3.3 yrs53.9
UNKNOWN169201Substation-Adjacent115 kV100 MW3.3 yrs52.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for TAP140589, Finney County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.