Greenfield (UNKNOWN124617 - KANSAS WEST)

Greenfield

VIGO, Indiana · MISO

DC Readiness
56.9
Good / 100

At a glance

Greenfield (UNKNOWN124617 - KANSAS WEST) is a greenfield datacenter candidate site in VIGO, Indiana, scoring 56.9/100 DC Readiness — 26th of 159 scored sites in the county. Its nearest substation is UNKNOWN124617. It sits in the MISO grid region, where interconnection has averaged 3.0 years from request to operation. GridCensus catalogs 600 MW of candidate capacity here.

Power & interconnection

Nearest substationUNKNOWN124617
Substation voltage345 kV
Available capacity600 MW

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth170
Avg queue wait3.0 yrs
Recent queue wait4.9 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPIndiana University Data Center
IXP distance64.4 mi
Fiber providers7
Fiber coverage80.8%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score68/100

Location context

Nearest datacenterNCSA Petascale Computing Facility
DC distance52.7 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.99¢/kWh
Industrial electricity8.65¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$5,886

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (UNKNOWN124617 - KANSAS WEST)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Greenfield (UNKNOWN124617 - KANSAS WEST) compare with other sites in VIGO?

Greenfield (UNKNOWN124617 - KANSAS WEST) ranks 26th of 159 scored candidate sites in VIGO. Its 56.9/100 is roughly in line with the county average of 52.9. It is roughly in line with the Indiana average of 54.0 and roughly in line with the national average of 53.2.

Against the Indiana average, its strongest sub-score is power availability (59 vs 33) and its weakest is fiber connectivity (70 vs 79). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Greenfield (UNKNOWN124617 - KANSAS WEST) to power, fiber and other datacenters?

The nearest mapped substation, UNKNOWN124617, is the closest grid connection point on record and operates at 345 kV. The nearest located transmission bottleneck is CIN23031_DRESSER_DRESS08ALE13_2_1 (MISO), 9 miles away. For connectivity, the nearest internet exchange facility is Indiana University Data Center at 64.4 miles. 7 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is NCSA Petascale Computing Facility, 52.7 miles away.

What are the flood, water and hazard risks at Greenfield (UNKNOWN124617 - KANSAS WEST)?

The site is in FEMA flood zone X, outside the Special Flood Hazard Area (minimal or moderate flood risk). At the county level, FEMA's National Risk Index rates VIGO "Relatively Moderate".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power20%
47
Fiber connectivity12%
70
Energy cost10%
50
Water risk7%
90
Natural hazard6%
68
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in VIGO, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN124617 - KANSAS WEST)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN124618Substation-Adjacent345 kV600 MW3.0 yrs67.3
UNKNOWN124759Substation-Adjacent345 kV600 MW3.0 yrs63.2
UNKNOWN124442Substation-Adjacent230 kV300 MW3.0 yrs62.8
UNKNOWN124449Substation-Adjacent230 kV300 MW3.0 yrs61.6
EC Near Sugar Creek PowerGreenfield——3.0 yrs58.8
EC Coal Vigo CountyGreenfield——3.0 yrs58.6
EC Near Sugar Creek PowerGreenfield——3.0 yrs58.4
EC FFE Vigo CountyGreenfield——3.0 yrs58.4

Greenfield (UNKNOWN124617 - KANSAS WEST): common questions

What is the DC Readiness score of Greenfield (UNKNOWN124617 - KANSAS WEST)?

Greenfield (UNKNOWN124617 - KANSAS WEST) scores 56.9/100 on the GridCensus DC Readiness scale, rated good. It ranks 26th of 159 scored sites in VIGO. The VIGO average is 52.9 and the Indiana average is 54.0.

What is the nearest substation to Greenfield (UNKNOWN124617 - KANSAS WEST)?

The nearest mapped substation is UNKNOWN124617, at 345 kV. GridCensus catalogs 600 MW of candidate capacity for the site.

What grid region is Greenfield (UNKNOWN124617 - KANSAS WEST) in?

Greenfield (UNKNOWN124617 - KANSAS WEST) is in the MISO region. Projects interconnecting there have averaged a 3.0-year wait from queue request to operation.

Is Greenfield (UNKNOWN124617 - KANSAS WEST) in a flood zone?

The site is in FEMA flood zone X, outside the Special Flood Hazard Area (minimal or moderate flood risk).

How far is Greenfield (UNKNOWN124617 - KANSAS WEST) from an internet exchange?

The nearest internet exchange facility is Indiana University Data Center, about 64.4 miles away; 7 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Greenfield (UNKNOWN124617 - KANSAS WEST), VIGO, IN”, https://gridcensus.com/datacenter-sites/indiana/vigo/greenfield-unknown124617-kansas-west-14a201ee (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Greenfield (UNKNOWN124617 - KANSAS WEST), VIGO is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.