Shoshone County, Idaho · WECC

DC Readiness
53.9
Fair / 100

TAP207670 is a substation-adjacent datacenter candidate site in Shoshone County, Idaho, interconnecting through WECC. It screens at 53.9/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP207670
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPCRALIDXX - Coeur d'Alene Central Office
IXP distance46.9 mi
Fiber providers2
Fiber coverage53.9%

Site characteristics

Land contactShoshone County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterNeutron - Coeur d'Alene
DC distance47.3 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity10.54¢/kWh
Industrial electricity5.94¢/kWh
Cooling degree days500
Heating degree days6,400
Land price / acre$8,542

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Personal property tax exemption on computer equipment.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track TAP207670

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
56
Fiber connectivity12%
61
Energy cost10%
50
Water risk7%
44
Natural hazard6%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Shoshone County, ranked by DC Readiness.

Sites near TAP207670
SiteTypeVoltageCapacityQueue waitScore
TAFTSubstation-Adjacent500 kV1,000 MW3.3 yrs64.7
OZ ShoshoneGreenfield——2.0 yrs62.3
PINE CREEKSubstation-Adjacent230 kV300 MW6.9 yrs61.6
EC FFE Shoshone CountyGreenfield——2.0 yrs56.7
UNKNOWN204941Substation-Adjacent115 kV100 MW6.9 yrs56.2
SILVERTONSubstation-Adjacent69 kV50 MW6.9 yrs54.2
UNKNOWN207669Substation-Adjacent69 kV50 MW6.9 yrs54.2
UNKNOWN205026Substation-Adjacent69 kV50 MW6.9 yrs54.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.