Substation-Adjacent site at 30.666, -83.069
Substation-AdjacentEchols, Georgia · SERC
At a glance
Substation-Adjacent site at 30.666, -83.069 is a substation-adjacent datacenter candidate site in Echols, Georgia, scoring 54.2/100 DC Readiness — 1st of 4 scored sites in the county. Its nearest substation is UNKNOWN111570 (0 mi, 115 kV). It sits in the SERC grid region and the GEORGIA POWER CO service territory, where interconnection has averaged 5.8 years from request to operation. GridCensus catalogs 100 MW of candidate capacity here.
Power & interconnection
Speed to power
Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
Active incentives; Georgia Power courts large load with bring-your-own clean-energy options.
Georgia Power billing/contract rules apply to very large loads.
Incentive detail: Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.
Site location
Get alerts
Track UNKNOWN111570
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
How does Substation-Adjacent site at 30.666, -83.069 compare with other sites in Echols?
Substation-Adjacent site at 30.666, -83.069 ranks 1st of 4 scored candidate sites in Echols. Its 54.2/100 is roughly in line with the county average of 51.4. It is roughly in line with the Georgia average of 57.1 and roughly in line with the national average of 53.2.
Against the Georgia average, its strongest sub-score is power availability (56 vs 50) and its weakest is fiber connectivity (54 vs 73). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.
How close is Substation-Adjacent site at 30.666, -83.069 to power, fiber and other datacenters?
The nearest mapped substation, UNKNOWN111570, is about 0 miles away and operates at 115 kV. For connectivity, the nearest internet exchange facility is EdgeConneX Tallahassee (EDCTAL01) at 77.6 miles. 5 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is EdgeConneX Tallahassee (EDCTAL01), 77.6 miles away.
What are the flood, water and hazard risks at Substation-Adjacent site at 30.666, -83.069?
At the county level, FEMA's National Risk Index rates Echols "Relatively High".
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Echols, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN111569 | Substation-Adjacent | 115 kV | 100 MW | 5.8 yrs | 53.8 |
| OZ Echols | Greenfield | — | — | 5.8 yrs | 50.0 |
| Greenfield (UNKNOWN111569 - UNKNOWN176931) | Greenfield | 115 kV | 100 MW | 5.8 yrs | 47.4 |
Substation-Adjacent site at 30.666, -83.069: common questions
What is the DC Readiness score of Substation-Adjacent site at 30.666, -83.069?
Substation-Adjacent site at 30.666, -83.069 scores 54.2/100 on the GridCensus DC Readiness scale, rated fair. It ranks 1st of 4 scored sites in Echols. The Echols average is 51.4 and the Georgia average is 57.1.
What is the nearest substation to Substation-Adjacent site at 30.666, -83.069?
The nearest mapped substation is UNKNOWN111570, about 0 miles away, at 115 kV. GridCensus catalogs 100 MW of candidate capacity for the site.
Which electric utility serves Substation-Adjacent site at 30.666, -83.069?
GEORGIA POWER CO (investor owned) holds the retail service territory that contains the site; its holding company is SOUTHERN COMPANY.
What grid region is Substation-Adjacent site at 30.666, -83.069 in?
Substation-Adjacent site at 30.666, -83.069 is in the SERC region. Projects interconnecting there have averaged a 5.8-year wait from queue request to operation.
How far is Substation-Adjacent site at 30.666, -83.069 from an internet exchange?
The nearest internet exchange facility is EdgeConneX Tallahassee (EDCTAL01), about 77.6 miles away; 5 fiber providers report service at the location.
Related pages
About this data
Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “Substation-Adjacent site at 30.666, -83.069, Echols, GA”, https://gridcensus.com/datacenter-sites/georgia/echols/unknown111570-a2a63418 (data as of October 10, 2026).
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
Every site and score for Substation-Adjacent site at 30.666, -83.069, Echols is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.