Datacenter Sites in Burke County, Georgia

Burke County has 32 scored datacenter candidate sites averaging 60.5/100 DC Readiness, with a catalogued aggregate of 9,800 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

32
Candidate sites
60.5/100
Avg DC Readiness
9,800 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating

Site-selection context for Burke County

Yessales_tax_exemption
Datacenter tax incentive
12.11¢/kWh
Commercial electricity
10.79¢/kWh
Industrial electricity
5
Fiber providers
Low-Medium
Water stress
$2,857
Land price / acre
2,200
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp

Incentive detail: Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.

By site type

Top datacenter sites in Burke County

Top datacenter sites in Burke County
SiteTypeVoltageCapacityQueue waitScore
WILSONSubstation-Adjacent230 kV300 MW3.7 yrs67.4
VOGTLESubstation-Adjacent500 kV1,000 MW3.7 yrs67.4
Greenfield (WEST MCINTOSH - UNKNOWN155812)Greenfield500 kV1,000 MW3.7 yrs66.5
UNKNOWN116828Substation-Adjacent115 kV100 MW3.7 yrs65.8
UNKNOWN157041Substation-Adjacent230 kV300 MW3.7 yrs65.3
Greenfield (THOMSON PRIMARY - VOGTLE)Greenfield500 kV1,000 MW3.7 yrs64.9
UNKNOWN112720Substation-Adjacent230 kV300 MW3.7 yrs64.5
TAP141833Substation-Adjacent115 kV100 MW3.7 yrs64.0
UNKNOWN112721Substation-Adjacent115 kV100 MW3.7 yrs63.8
Greenfield (WARTHEN SUBSTATION - UNKNOWN15)Greenfield500 kV1,000 MW3.7 yrs62.6
UNKNOWN120809Substation-Adjacent115 kV100 MW3.7 yrs62.3
Greenfield (THOMSON PRIMARY - VOGTLE)Greenfield500 kV1,000 MW3.7 yrs62.0
Greenfield (UNKNOWN113449 - UNKNOWN157041)Greenfield230 kV300 MW3.7 yrs62.0
Greenfield (WARTHEN SUBSTATION - UNKNOWN15)Greenfield500 kV1,000 MW3.7 yrs61.6
Greenfield (UNKNOWN113449 - UNKNOWN157041)Greenfield230 kV300 MW3.7 yrs61.0
Greenfield (WILSON - UNKNOWN112720)Greenfield230 kV300 MW3.7 yrs60.9
UNKNOWN112723Substation-Adjacent115 kV100 MW3.7 yrs60.8
UNKNOWN112722Substation-Adjacent115 kV100 MW3.7 yrs60.6
Greenfield (UNKNOWN113367 - UNKNOWN172551)Greenfield230 kV300 MW3.7 yrs60.1
TAP169087Substation-Adjacent115 kV100 MW3.7 yrs60.0
UNKNOWN116830Substation-Adjacent115 kV100 MW3.7 yrs59.6
OZ BurkeGreenfield5.8 yrs58.9
OZ BurkeGreenfield5.8 yrs58.7
UNKNOWN112719Substation-Adjacent115 kV100 MW3.7 yrs58.6
Greenfield (UNKNOWN112719 - TAP141802)Greenfield115 kV100 MW3.7 yrs58.5

Burke County datacenter FAQ

How many datacenter sites are in Burke County?
32 scored datacenter candidate sites, averaging 60.5/100 DC Readiness.
Does Burke County offer datacenter tax incentives?
Sales tax exemption on data processing equipment; investment tax credits for $150M+ projects.
What is the natural-hazard risk in Burke County?
FEMA's National Risk Index rates Burke County as "Relatively High" (score 40).
What are industrial electricity rates in Burke County?
Average industrial electricity is 10.79¢/kWh and commercial is 12.11¢/kWh in Burke County.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Burke County, Georgia. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.