Skip to content
Gridcensus

Greenfield (PHOENIX - COVENTRY)

Greenfield

Washtenaw County, Florida · SERC

DC Readiness
59.0
Good / 100

Greenfield (PHOENIX - COVENTRY) is a greenfield datacenter candidate site in Washtenaw County, Florida, interconnecting through SERC. It screens at 59.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationPHOENIX
Substation voltage120 kV
Available capacity100 MW

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPSynergy Fiber
IXP distance8.5 mi
Fiber providers17
Fiber coverage41.5%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterSynergy Fiber
DC distance8.5 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.37¢/kWh
Industrial electricity4.89¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$7,616

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (PHOENIX - COVENTRY)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
29
Speed to power20%
71
Fiber connectivity12%
78
Energy cost10%
50
Water risk7%
94
Natural hazard6%
75
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Washtenaw County, ranked by DC Readiness.

Sites near Greenfield (PHOENIX - COVENTRY)
SiteTypeVoltageCapacityQueue waitScore
MILANSubstation-Adjacent345 kV600 MW3.8 yrs64.8
COVENTRYSubstation-Adjacent345 kV600 MW3.8 yrs64.5
EC Near University of MichiganGreenfield——2.2 yrs63.7
EC Near East. Michigan Univ. Heating PlantGreenfield——2.2 yrs63.3
OZ WashtenawGreenfield——2.2 yrs63.1
MAJESTICSubstation-Adjacent345 kV600 MW3.8 yrs63.1
OZ WashtenawGreenfield——2.2 yrs62.7
EC Near GRS LyonGreenfield——2.2 yrs61.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (PHOENIX - COVENTRY), Washtenaw County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.