Datacenter Sites in Volusia County, Florida
Volusia County has 158 scored datacenter candidate sites averaging 55.0/100 DC Readiness, with a catalogued aggregate of 17,383 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
158
Candidate sites
55.0/100
Avg DC Readiness
17,383 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Volusia County
Yessales_tax_exemption
Datacenter tax incentive
11.55¢/kWh
Commercial electricity
8.45¢/kWh
Industrial electricity
17
Fiber providers
Low-Medium
Water stress
$13,409
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Volusia County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN108722 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.1 |
| SANFORD | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.0 |
| TAP155973 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 72.1 |
| DEBARY | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 72.0 |
| TAP155974 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 70.9 |
| UNKNOWN108716 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 70.6 |
| DEADEND167105 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 70.6 |
| DELTONA | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 69.6 |
| UNKNOWN120545 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 69.1 |
| UNKNOWN108720 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 68.2 |
| Greenfield (UNKNOWN150864 - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 68.0 |
| Greenfield (DUVAL - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 67.8 |
| DELAND | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 67.3 |
| UNKNOWN150864 | Substation-Adjacent | 500 kV | 1,000 MW | 3.6 yrs | 67.2 |
| UNKNOWN108714 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 67.1 |
| UNKNOWN108727 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.9 |
| GENERAL ELECTRIC | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.8 |
| G E TURNER | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.8 |
| UNKNOWN120538 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.5 |
| PORT ORANGE | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.3 |
| UNKNOWN108715 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.2 |
| DEADEND167104 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.2 |
| UNKNOWN120549 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.1 |
| Greenfield (UNKNOWN150864 - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 66.0 |
| Greenfield (TAP142184 - VOLUSIA) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 66.0 |
Volusia County datacenter FAQ
- How many datacenter sites are in Volusia County?
- 158 scored datacenter candidate sites, averaging 55.0/100 DC Readiness.
- Does Volusia County offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Volusia County?
- FEMA's National Risk Index rates Volusia County as "Very High" (score 55).
- What are industrial electricity rates in Volusia County?
- Average industrial electricity is 8.45¢/kWh and commercial is 11.55¢/kWh in Volusia County.
Dataset updated . Screening estimates derived from public data sources.