OZ Franklin

Greenfield

Franklin County, Florida · SERC

DC Readiness
49.2
Fair / 100

OZ Franklin is a greenfield datacenter candidate site in Franklin County, Florida, interconnecting through SERC. It screens at 49.2/100 DC Readiness and a 3.6 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.12¢/kWh
UtilityDUKE ENERGY FLORIDA, LLCinvestor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.6 yrs
Recent queue wait3.3 yrs
Completion rate26%
Withdrawal rate74%

Connectivity

Nearest IXPEdgeConneX Tallahassee (EDCTAL01)
IXP distance52.0 mi
Fiber providers3
Fiber coverage27.2%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance366.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerTiitf/Ag-Forestry
Land contactFranklin County Assessor
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands

Risk & environment

Environmental constraintModerate (40/100)
Flood zoneZone A (SFHA)
Water stress (WRI)1.20
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score20/100
Construction cost index53.5 (avg 100)

Location context

Nearest datacenterEdgeConneX Tallahassee (EDCTAL01)
DC distance52.0 mi
Nearest rail6.2 mi
Nearest gas pipeline3.9 mi
Nearest fiber route97.2 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.43¢/kWh
Industrial electricity9.33¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$6,207

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 4 nearby

Get alerts

Track OZ Franklin

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
74
Fiber connectivity12%
12
Energy cost10%
89
Water risk7%
76
Natural hazard6%
20
Buildability7%
15
Labor market4%
50
DC cluster4%
40
Land / acreage3%
40
Construction cost3%
100
Gas pipeline2%
88
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Franklin County, ranked by DC Readiness.

Sites near OZ Franklin
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN120978Substation-Adjacent69 kV50 MW1.0 yrs54.4
TAP143286Substation-Adjacent69 kV50 MW1.0 yrs54.0
CARRABELLESubstation-Adjacent69 kV50 MW1.0 yrs53.8
Old Carrabelle Water PlantIndustrial1.0 yrs49.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.