Greenfield (LAKE PARK - FOREST JUNCTION)

Greenfield

Calumet County, Florida · SERC

DC Readiness
60.2
Good / 100

Greenfield (LAKE PARK - FOREST JUNCTION) is a greenfield datacenter candidate site in Calumet County, Florida, interconnecting through SERC. It screens at 60.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationLAKE PARK
Substation voltage138 kV
Available capacity100 MW

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPark data centers - Green Bay, WI
IXP distance5.1 mi
Fiber providers5
Fiber coverage46.7%

Site characteristics

Site typeGreenfield

Risk & environment

Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score78/100

Location context

Nearest datacenterInvolta DC
DC distance5.1 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.25¢/kWh
Industrial electricity8.23¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$8,232

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
72
Fiber connectivity12%
74
Energy cost10%
50
Water risk8%
94
Natural hazard8%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Calumet County, ranked by DC Readiness.

Sites near Greenfield (LAKE PARK - FOREST JUNCTION)
SiteTypeVoltageCapacityQueue waitScore
FOREST JUNCTIONSubstation-Adjacent345 kV600 MW2.8 yrs66.3
CYPRESSSubstation-Adjacent345 kV600 MW2.8 yrs66.1
EC Coal Calumet CountyGreenfield1.4 yrs64.5
TAP139565Substation-Adjacent138 kV100 MW2.8 yrs63.1
LAKE PARKSubstation-Adjacent138 kV100 MW2.8 yrs63.0
TAP139564Substation-Adjacent138 kV100 MW2.8 yrs63.0
MEADOWSSubstation-Adjacent138 kV100 MW2.8 yrs62.9
MELISSASubstation-Adjacent138 kV100 MW2.8 yrs61.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen