Clearlake Rd & Michigan Blvd

Industrial

Brevard County, Florida · SERC

DC Readiness
54.7
Fair / 100

At a glance

Clearlake Rd & Michigan Blvd is an industrial datacenter candidate site in Brevard County, Florida, scoring 54.7/100 DC Readiness — 93rd of 122 scored sites in the county. It sits in the SERC grid region and the FLORIDA POWER & LIGHT CO service territory, where interconnection has averaged 3.7 years from request to operation.

Power & interconnection

UtilityFLORIDA POWER & LIGHT COinvestor ownedfavorable to large load · terms ≥ 50 MWLarge Load Contract Service (LLCS, ≥50 MW) · 90% min take · 20 yr

Speed to power

Interconnection outlookModerate
≈ 4.6 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.7 yrs
Recent queue wait4.6 yrs
Completion rate26%
Withdrawal rate74%

Connectivity

Nearest IXPSD Data Center
IXP distance9.6 mi
Fiber providers9
Fiber coverage58.3%

Site characteristics

Site typeIndustrial
Land contactBrevard County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low-Medium
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score45/100

Location context

Nearest datacenterSD Data Center
DC distance9.6 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.02¢/kWh
Industrial electricity8.73¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$7,712

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Clearlake Rd & Michigan Blvd

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Clearlake Rd & Michigan Blvd compare with other sites in Brevard County?

Clearlake Rd & Michigan Blvd ranks 93rd of 122 scored candidate sites in Brevard County. Its 54.7/100 is roughly in line with the county average of 56.9. It is roughly in line with the Florida average of 56.0 and roughly in line with the national average of 53.2.

Against the Florida average, its strongest sub-score is fiber connectivity (83 vs 73) and its weakest is power availability (30 vs 41). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Clearlake Rd & Michigan Blvd to power, fiber and other datacenters?

For connectivity, the nearest internet exchange facility is SD Data Center at 9.6 miles. 9 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is SD Data Center, 9.6 miles away.

What are the flood, water and hazard risks at Clearlake Rd & Michigan Blvd?

At the county level, FEMA's National Risk Index rates Brevard County "Very High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
65
Fiber connectivity12%
83
Energy cost10%
50
Water risk7%
76
Natural hazard6%
45
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Brevard County, ranked by DC Readiness.

Sites near Clearlake Rd & Michigan Blvd
SiteTypeVoltageCapacityQueue waitScore
POINSETTSubstation-Adjacent500 kV1,000 MW3.7 yrs67.2
CAPE CANAVERALSubstation-Adjacent230 kV300 MW3.7 yrs67.2
VIERASubstation-Adjacent230 kV300 MW3.7 yrs65.3
UNKNOWN120180Substation-Adjacent230 kV300 MW3.7 yrs64.8
SARNOSubstation-Adjacent230 kV300 MW3.7 yrs64.7
MALABARSubstation-Adjacent230 kV300 MW3.7 yrs64.0
UNKNOWN120277Substation-Adjacent230 kV300 MW3.7 yrs63.6
UNKNOWN108545Substation-Adjacent230 kV300 MW3.7 yrs63.4

Clearlake Rd & Michigan Blvd: common questions

What is the DC Readiness score of Clearlake Rd & Michigan Blvd?

Clearlake Rd & Michigan Blvd scores 54.7/100 on the GridCensus DC Readiness scale, rated fair. It ranks 93rd of 122 scored sites in Brevard County. The Brevard County average is 56.9 and the Florida average is 56.0.

Which electric utility serves Clearlake Rd & Michigan Blvd?

FLORIDA POWER & LIGHT CO (investor owned) holds the retail service territory that contains the site; its holding company is NEXTERA ENERGY INC.

What grid region is Clearlake Rd & Michigan Blvd in?

Clearlake Rd & Michigan Blvd is in the SERC region. Projects interconnecting there have averaged a 3.7-year wait from queue request to operation.

How far is Clearlake Rd & Michigan Blvd from an internet exchange?

The nearest internet exchange facility is SD Data Center, about 9.6 miles away; 9 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Clearlake Rd & Michigan Blvd, Brevard County, FL”, https://gridcensus.com/datacenter-sites/florida/brevard-county/clearlake-rd-michigan-blvd-6cc2c39d (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Clearlake Rd & Michigan Blvd, Brevard County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.